4832 N NORWICH AVE 91403
Certificate Information: 4832 N NORWICH AVE 91403
- Application / Permit
- 19014-10000-01441
- Plan Check / Job No.
- B19LA05823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY (1240 SQFT.) ADDITION TO INCLUDE -- (2)-BEDROOMS, (2)-BATHROOMS, A KITCHEN REMODEL AND A (2)-CAR GARAGE.
- Permit Issued
- Issued on 6/20/2019
- Issuing Office
- Metro
- Current Status
- Issued on 6/20/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | VU NGUYEN |
| Green Plans Picked Up | 4/22/2019 | APPLICANT |
| Corrections Issued | 4/29/2019 | VU NGUYEN |
| Quality Review Completed | 5/8/2019 | MICHAEL PEREZ |
| Building Plans Picked Up | 5/9/2019 | APPLICANT |
| Plan Check Approved | 6/14/2019 | VU NGUYEN |
| Issued | 6/20/2019 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2019 | ELENA LOPEZ |
| Green Code | Cleared | 5/14/2019 | SARAH ABOULHOSN |
| Sewer availability | Cleared | 5/14/2019 | ELENA LOPEZ |
| Low Impact Development | Cleared | 6/13/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/13/2019 | ELAINE LEI |
Contact Information
| Contractor | La Rocca Builders Inc; Lic. No.: 934161-B | 565 N ARDEN BLVD LOS ANGELES, CA 90004 |
| Engineer | Kim,, Taewon; Lic. No.: C80632 | 28000 S WESTERN AVE UNIT 209 SAN PEDRO, CA 90732 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/15/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 7/19/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Wood Frame | 7/19/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 7/25/2019 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/4/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/4/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 9/4/2019 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 9/4/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 9/4/2019 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/4/2019 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 9/13/2019 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 9/13/2019 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 9/13/2019 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 9/13/2019 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 9/23/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 9/27/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 10/17/2019 | Partial Approval | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/14/2020 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 2/19/2020 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 2/19/2020 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2020 | Partial Approval | JEFFREY PARD |
| PLUMBING-Rough | 2/28/2020 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2020 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 3/5/2020 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 6/11/2020 | Approved | THOMAS FINNILA |
| HVAC-Rough | 6/11/2020 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 6/11/2020 | Approved | THOMAS FINNILA |
| Drywall Nailing | 10/14/2020 | Approved | CHARLES POWELL |
| Green Building Final | 10/14/2020 | Not Ready for Inspection | CHARLES POWELL |
| MERV13>=Final | 10/14/2020 | Not Ready for Inspection | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Not Ready | CHARLES POWELL |
| Smoke Detectors | 10/14/2020 | Not Ready for Inspection | CHARLES POWELL |
| Final | 11/5/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/5/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Final | 11/5/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 11/5/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 11/5/2025 | Approved | JACK KARGODORIAN |
| Final | 11/17/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 11/17/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Pre-Inspection | 12/9/2025 | Approved | JACK KARGODORIAN |