336-338 E PERSHING DR 90293

Certificate Information: 336-338 E PERSHING DR 90293

Application / Permit
19014-10000-01422
Plan Check / Job No.
B19LA05724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF DECK AND INTERIOR REMODEL TO EXISTING SFD . COVERSION OF EXISTING FIRST FLOOR INTO ACCESSORY DWELLING UNIT PER AB-494 AND SB-229. "COMPLY WITH DEPARTMENT ORDER effective date 12/27/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case 837653.
Permit Issued
Issued on 7/19/2019
Issuing Office
Metro
Current Status
CofO Issued on 4/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2019 APPLICANT
Green Plans Picked Up 4/3/2019 APPLICANT
Assigned to Plan Check Engineer 4/4/2019 ZAW HAN
Corrections Issued 4/8/2019 ZAW HAN
Quality Review Completed 4/11/2019 FELIX FIGUEROA
Building Plans Picked Up 4/12/2019 APPLICANT
Applicant returned to address corrections 7/1/2019 ZAW HAN
Plan Check Approved 7/18/2019 ZAW HAN
Issued 7/19/2019 LADBS
CofO in Progress 3/10/2020 MARIAN PODPORA
Permit Finaled 4/7/2020 BRUCE TODD
Permit Finaled 4/7/2020 BRUCE TODD
CofO Issued 4/7/2020 BRUCE TODD

Permit Application Clearance Information

CPC Cleared 6/7/2019 NOAH MCCOY
Coastal Zone Cleared 6/7/2019 NOAH MCCOY
Specific Plan Cleared 6/7/2019 MOHAMMAD HASAN
Green Code Cleared 6/25/2019 SARAH ABOULHOSN
Housing rent stabilization Cleared 6/25/2019 DAN HAECKER
ZI Cleared 6/25/2019 SARAHI ORTEGA
Address approval Cleared 7/1/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 7/1/2019 ERIK BEASLEY
Grading Pre-Inspection Cleared 7/18/2019 JONATHAN HOM

Contact Information

Contractor Owner-Builder       ,
Engineer Orland,, James Curtiss; Lic. No.: C22024 660 18TH ST      MANHATTAN BEACH, CA 90266

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/9/2019 Not Ready for Inspection MARIAN PODPORA
Sewer 8/9/2019 Not Ready for Inspection MARIAN PODPORA
ELECTRICAL-Rough 8/16/2019 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 8/28/2019 Partial Approval MARIAN PODPORA
PLUMBING-Rough 8/28/2019 Partial Approval MARIAN PODPORA
Sewer 8/28/2019 Approved MARIAN PODPORA
BUILDING-Rough-Frame 10/10/2019 Not Ready for Inspection MARIAN PODPORA
Green Building Rough 10/10/2019 Not Ready for Inspection MARIAN PODPORA
METHANE-Rough 10/10/2019 Approved MARIAN PODPORA
BUILDING-Rough-Frame 10/22/2019 Corrections Issued MARIAN PODPORA
Green Building Rough 10/22/2019 Corrections Issued MARIAN PODPORA
Wood Frame 10/22/2019 Corrections Issued MARIAN PODPORA
ELECTRICAL-Rough 10/30/2019 Not Ready for Inspection MARIAN PODPORA
BUILDING-Rough-Frame 12/5/2019 Approved MARIAN PODPORA
ELECTRICAL-Rough 12/5/2019 Partial Approval MARIAN PODPORA
Green Building Rough 12/5/2019 Approved MARIAN PODPORA
HVAC-Rough 12/5/2019 Approved MARIAN PODPORA
Wood Frame 12/5/2019 Approved MARIAN PODPORA
HVAC-Rough 12/27/2019 Approved MARIAN PODPORA
Insulation 12/27/2019 Approved MARIAN PODPORA
Interior/Exterior Lathing 12/27/2019 Partial Approval MARIAN PODPORA
Drywall Nailing 1/7/2020 Approved MARIAN PODPORA
Interior/Exterior Lathing 1/22/2020 Not Ready for Inspection MARIAN PODPORA
Shower Pan 1/22/2020 Approved MARIAN PODPORA
Interior/Exterior Lathing 1/23/2020 Approved MARIAN PODPORA
ELECTRICAL-Final 2/27/2020 Not Ready for Inspection MARIAN PODPORA
ELECTRICAL-Rough 2/27/2020 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Final 2/27/2020 Not Ready for Inspection MARIAN PODPORA
Smoke Detectors 2/27/2020 Not Ready for Inspection MARIAN PODPORA
ELECTRICAL-Rough 2/28/2020 Not Ready for Inspection MARIAN PODPORA
PLUMBING-Final 2/28/2020 Not Ready for Inspection MARIAN PODPORA
Service/Power Release 2/28/2020 Partial Approval MARIAN PODPORA
Final 3/4/2020 Not Ready for Inspection MARIAN PODPORA
Footing/Foundation/Slab 3/4/2020 Approved MARIAN PODPORA
Green Building Final 3/4/2020 Not Ready for Inspection MARIAN PODPORA
METHANE-Barrier 3/4/2020 Approved MARIAN PODPORA
METHANE-Subgrade 3/4/2020 Approved MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 3/4/2020 SGSOV Approved MARIAN PODPORA
Service/Power Release 3/4/2020 Partial Approval MARIAN PODPORA
Smoke Detectors 3/4/2020 Approved MARIAN PODPORA
Pre-Inspection 3/5/2020 Corrections Issued MARIAN PODPORA
Service/Power Release 3/5/2020 Partial Approval MARIAN PODPORA
ELECTRICAL-Final 3/9/2020 Approved MARIAN PODPORA
Final 3/9/2020 OK to Issue CofO MARIAN PODPORA
Green Building Final 3/9/2020 Approved MARIAN PODPORA