1877-1879 W 38TH PL 90062

Certificate Information: 1877-1879 W 38TH PL 90062

Application / Permit
19014-10000-01420
Plan Check / Job No.
B19LA05719
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
REMODEL AND 2ND STORY ADDITION TO EXISTING DUPLEX
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 4/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/20/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 ANA AVELAR
Corrections Issued 4/17/2019 ANA AVELAR
Quality Review Completed 4/17/2019 KESETE HAREGOT
Building Plans Picked Up 4/23/2019 APPLICANT
Green Plans Picked Up 4/23/2019 APPLICANT
Applicant returned to address corrections 7/9/2019 MONICA RAMIREZ
Applicant returned to address corrections 3/30/2021 MONICA RAMIREZ
Applicant returned to address corrections 7/13/2021 MONICA RAMIREZ
Applicant returned to address corrections 7/15/2021 MONICA RAMIREZ
Applicant returned to address corrections 7/19/2021 MONICA RAMIREZ
Applicant returned to address corrections 8/4/2021 MONICA RAMIREZ
Applicant returned to address corrections 8/20/2021 MONICA RAMIREZ
Applicant returned to address corrections 10/1/2021 MONICA RAMIREZ
Plan Check Approved 10/5/2021 MONICA RAMIREZ
Issued 10/5/2021 APPLICANT
CofO in Progress 3/31/2023 SABAS ALONSO
Permit Finaled 4/2/2023 DEROLD HAUFF
CofO Issued 4/2/2023 DEROLD HAUFF
Permit Finaled 4/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 6/26/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 12/8/2020 THOMAS LANG
Low Impact Development Cleared 7/13/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/19/2021 WALLIE JONG
Green Code Cleared 9/30/2021 SARAH ABOULHOSN

Contact Information

Contractor Owner-Builder       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 20626 HAYNES ST      WINNETKA, CA 91306

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/13/2021 Partial Inspection SABAS ALONSO
Deputy Drilled-In Anchors 1/21/2022 Conditional Approval SABAS ALONSO
Underground Mechanical 2/2/2022 No Access for Inspection SABAS ALONSO
Underground Mechanical 2/7/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 2/10/2022 Partial Approval SABAS ALONSO
Underground Mechanical 2/10/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Corrections Issued SABAS ALONSO
Deputy Wood Construction 2/18/2022 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/5/2022 Partial Approval SABAS ALONSO
Wood Frame 4/5/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 5/2/2022 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 5/2/2022 Corrections Issued SABAS ALONSO
PLUMBING-Rough 5/2/2022 Approved SABAS ALONSO
ELECTRICAL-Rough 5/5/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Not Ready for Inspection HORACE FULTZ
Green Building Rough 5/5/2022 Approved SABAS ALONSO
HVAC-Rough 5/20/2022 Approved HORACE FULTZ
Interior/Exterior Lathing 5/20/2022 Partial Approval HORACE FULTZ
Insulation 6/6/2022 Approved SABAS ALONSO
Drywall Nailing 6/30/2022 Corrections Issued HORACE FULTZ
BUILDING-Rough-Frame 7/8/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 10/12/2022 Approved STUART CHAPMAN
Final 10/12/2022 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 10/12/2022 Approved STUART CHAPMAN
Green Building Final 10/12/2022 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/12/2022 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/12/2022 Not Ready for Inspection STUART CHAPMAN
Final 11/2/2022 Corrections Issued SABAS ALONSO
Green Building Final 11/2/2022 Corrections Issued SABAS ALONSO
Smoke Detectors 11/2/2022 Approved SABAS ALONSO
Final 3/30/2023 OK to Issue CofO SABAS ALONSO
Green Building Final 3/30/2023 Approved SABAS ALONSO