3828 N AMESBURY ROAD 90027
Certificate Information: 3828 N AMESBURY ROAD 90027
- Application / Permit
- 19014-10000-01362
- Plan Check / Job No.
- B19LA05476
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) 2 STORY SFD BY ENCLOSING (E) FIRST FLOOR COVERED PORCH (158 SF) & SECOND FLOOR COVERED PORCH (206 SF) TO EXPAND DINING ROOM AND CREATE ADDITIONAL RESTROOM AT FIRST FLOOR; CREATE NEW BEDROOM, BATHROOM, AND CLOSET AT SECOND FLOOR.
- Permit Issued
- Issued on 9/23/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2019 | JEFFREY MACHADO |
| Corrections Issued | 4/2/2019 | JEFFREY MACHADO |
| Quality Review Completed | 4/8/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 4/25/2019 | APPLICANT |
| Green Plans Picked Up | 4/25/2019 | APPLICANT |
| Plan Check Approved | 8/28/2019 | JEFFREY MACHADO |
| Issued | 9/23/2019 | LADBS |
| CofO in Progress | 8/12/2020 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/2/2023 | DEROLD HAUFF |
| CofO Issued | 2/2/2023 | DEROLD HAUFF |
| Permit Finaled | 2/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/17/2019 | ELAINE LEI |
| BHO/Hillside ordinance | Cleared | 5/17/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2019 | JEANIE LAM |
| Sewer availability | Cleared | 5/17/2019 | JEANIE LAM |
| Green Code | Cleared | 8/8/2019 | JEFFREY MACHADO |
| Low Impact Development | Cleared | 8/8/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/8/2019 | JEANIE LAM |
| GPI Written Notices | Cleared | 8/28/2019 | JEFFREY MACHADO |
| Grading Pre-Inspection | Cleared | 8/28/2019 | JEFFREY MACHADO |
Contact Information
| Contractor | Perkins Michael Construction; Lic. No.: 745473-B | 520 S SUNSET CANYON DRIVE BURBANK, CA 91501 |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 708 SOUTH REDONDO AVE MANHATTAN BEACH, CA 90266 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/6/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/19/2019 | Corrections Issued | ARTHUR SARGSYAN |
| PLUMBING-Rough | 12/19/2019 | Conditional Approval | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 1/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 1/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 1/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| Structural Steel Frame | 1/17/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/27/2020 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2020 | Partial Approval | JOSEPH MCGARRY |
| Green Building Rough | 1/31/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 1/31/2020 | Partial Approval | JOSEPH MCGARRY |
| Insulation | 1/31/2020 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 1/31/2020 | Partial Approval | JOSEPH MCGARRY |
| Shower Pan | 1/31/2020 | Corrections Issued | JOSEPH MCGARRY |
| Shower Pan | 2/5/2020 | Approved | BRAD BESCOS |
| Footing/Foundation/Slab | 3/2/2020 | Approved | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 3/3/2020 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 3/6/2020 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/27/2020 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/27/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/27/2020 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/27/2020 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/27/2020 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 6/11/2020 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/11/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/11/2020 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 9/9/2020 | Corrections Issued | CHRIS CHRISTENSEN |