10040 N COVERT AVE 91042

Certificate Information: 10040 N COVERT AVE 91042

Application / Permit
19014-10000-01361
Plan Check / Job No.
B19LA05467
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Two-story, ground floor addition to (E) one-story SFD and interior remodel to create master bedroom on second floor and covered patio on ground floor. Scope of work to include addition and remodel of (E) Single Family Dwelling. All work per engineered design.
Permit Issued
Issued on 5/31/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 CHRISTOPHER KOMANCHECK
Corrections Issued 4/1/2019 MUKUL GUPTA
Green Plans Picked Up 4/1/2019 APPLICANT
Quality Review Completed 4/9/2019 JOSE RODRIGUEZ
Building Plans Picked Up 4/10/2019 APPLICANT
Plan Check Approved 5/22/2019 CHRISTOPHER KOMANCHECK
Issued 5/31/2019 LADBS
CofO in Progress 1/20/2021 DAVID MATSON
CofO Issued 2/27/2021 MICHAEL SMITH
Permit Finaled 2/27/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 4/15/2019 KAREN LE
Sewer availability Cleared 4/15/2019 KAREN LE
Grading Pre-Inspection Cleared 4/16/2019 PATRICK MISCHLICH
Green Code Cleared 4/30/2019 KHEDER ALRAZAA
Hydrant and Access approval Cleared 5/2/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 5/20/2019 ELENA LOPEZ
GPI Written Notices Cleared 5/20/2019 MUKUL GUPTA

Contact Information

Contractor So Cal Builders And Design Inc; Lic. No.: 990258-B 15335 MORRISON STREET #375      SHERMAN OAKS, CA 91403
Engineer Andrada,, Aprile Larracas; Lic. No.: C81097 27356 DEARBORN DRIVE      VALENCIA, CA 91354

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 6/11/2019 Approved MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 7/1/2019 Corrections Issued MATTHEW NELSON
Special/Order Compliance 7/1/2019 Approved BEAU COLLINS
Excavation/Setback/Form/Re-Bar 7/3/2019 No Access for Inspection MATTHEW NELSON
Special/Order Compliance 7/3/2019 No Access for Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 8/12/2019 Approved MATTHEW NELSON
Footing/Foundation/Slab 9/17/2019 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/3/2020 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2020 Corrections Issued MATTHEW NELSON
Special/Order Compliance 1/21/2020 Approved PIERRE VEGA
ELECTRICAL-Rough 3/17/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 3/17/2020 Not Ready for Inspection MATTHEW NELSON
Special/Order Compliance 3/17/2020 Approved PIERRE VEGA
Wood Frame 3/17/2020 Corrections Issued MATTHEW NELSON
ELECTRICAL-Rough 4/21/2020 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/21/2020 Corrections Issued MATTHEW NELSON
Special/Order Compliance 4/21/2020 Partial Inspection PIERRE VEGA
Wood Frame 4/21/2020 Corrections Issued MATTHEW NELSON
Special/Order Compliance 4/22/2020 Partial Inspection MATTHEW NELSON
Special/Order Compliance 4/29/2020 Approved MATTHEW NELSON
Special/Order Compliance 4/29/2020 Partial Approval PIERRE VEGA
Rough-Elec/Plmb/HVAC 5/12/2020 Approved MATTHEW NELSON
Insulation 5/26/2020 Approved MATTHEW NELSON
Drywall Nailing 6/16/2020 Partial Inspection MATTHEW NELSON
Drywall Nailing 7/1/2020 Approved MATTHEW NELSON
Shower Pan 7/8/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/14/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/21/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 12/21/2020 Not Ready for Inspection MATTHEW NELSON
Final 12/21/2020 Not Ready for Inspection MATTHEW NELSON
Green Building Final 12/21/2020 Corrections Issued MATTHEW NELSON
Green Building Rough 12/21/2020 Approved MATTHEW NELSON
HVAC-Final 12/21/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 12/21/2020 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/21/2020 SGSOV Approved MATTHEW NELSON
Smoke Detectors 12/21/2020 Approved MATTHEW NELSON
ELECTRICAL-Final 12/29/2020 Partial Approval MATTHEW NELSON
Green Building Final 12/29/2020 Not Ready for Inspection MATTHEW NELSON
Final 1/5/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Final 1/5/2021 Corrections Issued MATTHEW NELSON
ELECTRICAL-Final 1/8/2021 Approved MATTHEW NELSON
Final 1/8/2021 Partial Approval MATTHEW NELSON
Green Building Final 1/8/2021 Approved MATTHEW NELSON
HVAC-Final 1/8/2021 Approved MATTHEW NELSON