Deputy Reinf. Concrete
|
8/9/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
8/9/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
METHANE-Barrier
|
8/9/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
METHANE-Subgrade
|
8/9/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
8/10/2021
|
Corrections Issued
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/11/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/12/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/13/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/16/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/17/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
METHANE-Rough
|
8/17/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
8/17/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/18/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
8/18/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
METHANE-Barrier
|
8/18/2021
|
Approved
|
SORIN CIRSTOIU
|
|
METHANE-Subgrade
|
8/18/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/19/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/20/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
8/24/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
8/25/2021
|
Conditional Approval
|
JOHN DODGE
|
|
Deputy Shotcrete
|
8/26/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
8/27/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
8/27/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
8/27/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
8/31/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
8/31/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
9/1/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
9/1/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
9/2/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
9/2/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
9/3/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
9/3/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
9/17/2021
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
9/24/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
10/22/2021
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
10/22/2021
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
10/26/2021
|
Approved
|
NICK LAROCCA
|
|
Deputy Shotcrete
|
11/8/2021
|
Approved
|
NICK LAROCCA
|
|
Deputy Shotcrete
|
11/9/2021
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
11/9/2021
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
11/10/2021
|
Approved
|
NICK LAROCCA
|
|
Deputy Shotcrete
|
11/10/2021
|
Approved
|
NICK LAROCCA
|
|
Deputy Shotcrete
|
11/12/2021
|
Approved
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
11/16/2021
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
11/30/2021
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
12/16/2021
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
12/17/2021
|
Approved
|
NICK LAROCCA
|
|
Reinforced Concrete Frame
|
12/29/2021
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2021
|
Not Ready for Inspection
|
NICK LAROCCA
|
|
Excavation/Setback/Form/Re-Bar
|
1/3/2022
|
Partial Approval
|
NICK LAROCCA
|
|
Deputy Reinf. Concrete
|
1/6/2022
|
Approved
|
NICK LAROCCA
|
|
Footing/Foundation/Slab
|
2/11/2022
|
Not Ready for Inspection
|
JEFF BYTHEWAY
|
|
Reinforced Concrete Frame
|
2/14/2022
|
Partial Approval
|
JEFF BYTHEWAY
|
|
Deputy Reinf. Concrete
|
2/17/2022
|
Approved
|
JEFF BYTHEWAY
|
|
Deputy Wood Construction
|
3/22/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/22/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
3/23/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
3/24/2022
|
Approved
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
3/25/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/14/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
5/31/2022
|
Conditional Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/31/2022
|
Partial Approval
|
DAVID TSAU
|
|
Deputy Wood Construction
|
6/1/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
6/2/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
6/3/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/22/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Wood Construction
|
6/23/2022
|
Approved
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
7/7/2022
|
Approved
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/20/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2022
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/9/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Wood Frame
|
8/11/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/2/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
11/9/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
11/21/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
11/29/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Insulation
|
12/6/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Drywall Nailing
|
12/16/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Interior/Exterior Lathing
|
12/21/2022
|
Partial Approval
|
PAUL DAVIDSON
|
|
Drywall Nailing
|
2/16/2023
|
Partial Approval
|
DERRICK SPENCER
|
|
Final
|
7/20/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Footing/Foundation/Slab
|
7/20/2023
|
Approved
|
DERRICK SPENCER
|
|
Green Building Final
|
7/20/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
7/20/2023
|
Approved
|
DERRICK SPENCER
|
|
Reinforced Masonry Frame
|
7/20/2023
|
Approved
|
DERRICK SPENCER
|
|
SGSOV-Seismic Gas S/O Valve
|
7/20/2023
|
SGSOV Approved
|
DERRICK SPENCER
|
|
Smoke Detectors
|
7/20/2023
|
Approved
|
DERRICK SPENCER
|
|
Green Building Final
|
7/28/2023
|
Approved
|
DERRICK SPENCER
|
|
Final
|
8/2/2023
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Final
|
8/9/2023
|
OK to Issue CofO
|
DERRICK SPENCER
|