944 S HIGHLAND AVE 90036

Certificate Information: 944 S HIGHLAND AVE 90036

Application / Permit
19014-10000-01315
Plan Check / Job No.
B19LA05244
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED 20 X 18 GARAGE TO ADU AB 494 AND SB 229, ADD 3' X 13' STORAGE ROOM
Permit Issued
Issued on 8/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2019 APPLICANT
Assigned to Plan Check Engineer 4/4/2019 ADAM HEGAZI
Corrections Issued 4/5/2019 ADAM HEGAZI
Quality Review Completed 4/22/2019 JOSE RODRIGUEZ
Building Plans Picked Up 5/28/2019 APPLICANT
Green Plans Picked Up 5/28/2019 APPLICANT
Plan Check Approved 7/26/2019 ADAM HEGAZI
Issued 8/20/2019 LADBS
CofO in Progress 8/20/2021 CHRIS CHRISTENSEN
Permit Finaled 9/2/2021 DEROLD HAUFF
CofO Issued 9/2/2021 DEROLD HAUFF
Permit Finaled 9/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/12/2019 KAREN LE
CPC Cleared 6/12/2019 KIT AWAKUNI
Eng Process Fee Ord 176,300 Cleared 6/12/2019 KAREN LE
Hydrant and Access approval Cleared 6/12/2019 GILBERT URREA
Construction near power lines Cleared 6/27/2019 ERNEST FRESQUEZ
Green Code Cleared 7/2/2019 COLIN LOREDO
Low Impact Development Cleared 7/23/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/23/2019 JEANIE LAM
Sewer availability Cleared 7/23/2019 JEANIE LAM

Contact Information

Architect Yano,, Jennifer F.; Lic. No.: C35777       ,
Contractor Revel Construction Company; Lic. No.: 1029538-B 25165 SAGECREST CIR      STEVENSON RANCH, CA 91381
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 8/12/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 8/12/2020 Approved ARTHUR SARGSYAN
Green Building Rough 8/12/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 8/12/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 8/12/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/12/2020 Approved ARTHUR SARGSYAN
Insulation 8/18/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 8/18/2020 Partial Approval THOMAS LOGRASSO
Insulation 8/27/2020 Approved THOMAS LOGRASSO
Drywall Nailing 9/3/2020 Approved ARTHUR SARGSYAN
Sewer 12/11/2020 Approved JOSEPH MCGARRY
ELECTRICAL-Final 1/27/2021 Corrections Issued JOSEPH MCGARRY
ELECTRICAL-Final 5/6/2021 Approved CHRIS CHRISTENSEN
Final 5/6/2021 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/6/2021 Approved CHRIS CHRISTENSEN
Green Building Final 5/6/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 5/6/2021 Approved CHRIS CHRISTENSEN
METHANE-Barrier 5/6/2021 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 5/6/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/6/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/6/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/6/2021 Approved CHRIS CHRISTENSEN
Final 8/19/2021 OK to Issue CofO CHRIS CHRISTENSEN