942 S HIGHLAND AVE 90036

Certificate Information: 942 S HIGHLAND AVE 90036

Application / Permit
19014-10000-01314
Plan Check / Job No.
B19LA05244
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 STORY ADDITION 18' X 18' TO AN (E) SFD
Permit Issued
Issued on 8/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 5/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/14/2019 APPLICANT
Assigned to Plan Check Engineer 4/4/2019 ADAM HEGAZI
Corrections Issued 4/5/2019 ADAM HEGAZI
Quality Review Completed 4/22/2019 JOSE RODRIGUEZ
Building Plans Picked Up 5/28/2019 APPLICANT
Green Plans Picked Up 5/28/2019 APPLICANT
Plan Check Approved 7/26/2019 ADAM HEGAZI
Issued 8/20/2019 LADBS
CofO in Progress 4/29/2022 JOSEPH MCGARRY
Permit Finaled 5/4/2022 DEROLD HAUFF
CofO Issued 5/4/2022 DEROLD HAUFF
Permit Finaled 5/4/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 6/12/2019 KIT AWAKUNI
Eng Process Fee Ord 176,300 Cleared 6/12/2019 KAREN LE
Sewer availability Cleared 6/12/2019 KAREN LE
Green Code Cleared 7/2/2019 COLIN LOREDO
Low Impact Development Cleared 7/23/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/23/2019 JEANIE LAM

Contact Information

Architect Yano,, Jennifer F.; Lic. No.: C35777       ,
Contractor Revel Construction Company; Lic. No.: 1029538-B 25165 SAGECREST CIR      STEVENSON RANCH, CA 91381
Engineer Wavering,, Derek Evan; Lic. No.: S6239 1371 COLE LANE      UPLAND, CA 91784

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2020 Conditional Approval ARTHUR SARGSYAN
METHANE-Barrier 3/12/2020 Approved ARTHUR SARGSYAN
METHANE-Subgrade 3/12/2020 Approved ARTHUR SARGSYAN
Deputy Drilled-In Anchors 6/9/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 6/10/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 6/29/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 8/12/2020 Approved ARTHUR SARGSYAN
Green Building Rough 8/12/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 8/12/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 8/12/2020 Approved ARTHUR SARGSYAN
Wood Frame 8/12/2020 Approved ARTHUR SARGSYAN
Insulation 8/18/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 8/18/2020 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 8/27/2020 Partial Approval THOMAS LOGRASSO
Drywall Nailing 9/3/2020 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Not Ready CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/27/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 4/27/2021 Approved JOSEPH MCGARRY
Final 4/27/2021 Corrections Issued JOSEPH MCGARRY
Green Building Final 4/27/2021 Approved JOSEPH MCGARRY
HVAC-Final 4/27/2021 Approved JOSEPH MCGARRY
METHANE-Final 4/27/2021 Approved JOSEPH MCGARRY
METHANE-Rough 4/27/2021 Approved JOSEPH MCGARRY
PLUMBING-Final 4/27/2021 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/27/2021 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 4/27/2021 Approved JOSEPH MCGARRY
Final 4/29/2022 OK to Issue CofO JOSEPH MCGARRY