10243 W KLING ST 91602

Certificate Information: 10243 W KLING ST 91602

Application / Permit
19014-10000-01187
Plan Check / Job No.
B19LA04766
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW ADDITION ADU ACCESSORY DWELLING UNIT PER AB494 AND SB229
Permit Issued
Issued on 7/1/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2019 APPLICANT
Assigned to Plan Check Engineer 3/15/2019 SERGIO GUTIERREZ
Corrections Issued 3/19/2019 SERGIO GUTIERREZ
Quality Review Completed 4/2/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 4/4/2019 APPLICANT
Applicant returned to address corrections 5/8/2019 SERGIO GUTIERREZ
Green Plans Picked Up 6/7/2019 APPLICANT
Plan Check Approved 7/1/2019 SERGIO GUTIERREZ
Issued 7/1/2019 LADBS
CofO in Progress 11/4/2021 DANIEL DREW
Permit Finaled 8/29/2022 DANIEL ORRANTE
CofO Issued 8/29/2022 DANIEL ORRANTE
Permit Finaled 8/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/8/2019 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 5/8/2019 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/7/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 6/7/2019 JOHN CONNEALLY
Miscellaneous Cleared 6/7/2019 BLAYNE SUTTON-WILLS
Sewer availability Cleared 6/7/2019 ELENA LOPEZ
Green Code Cleared 6/19/2019 KHEDER ALRAZAA
Low Impact Development Cleared 6/26/2019 MITESH PATEL

Contact Information

Contractor Owner-Builder       ,
Engineer Cervantes,, Joaquin; Lic. No.: C70635 18800 AMAR RD STE B13      WALNUT, CA 91789

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/5/2019 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 9/5/2019 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/5/2019 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 4/14/2020 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Partial Approval RAYMOND KEHOE
Green Building Rough 4/14/2020 Approved RAYMOND KEHOE
Rough-Elec/Plmb/HVAC 4/14/2020 Approved RAYMOND KEHOE
Insulation 4/24/2020 Partial Approval RAYMOND KEHOE
Interior/Exterior Lathing 4/24/2020 Partial Approval RAYMOND KEHOE
Shower Pan 4/24/2020 Approved RAYMOND KEHOE
Deputy Wood Construction 4/29/2020 Approved RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Partial Approval RAYMOND KEHOE
Insulation 5/4/2020 Approved RAYMOND KEHOE
Interior/Exterior Lathing 5/4/2020 Partial Approval RAYMOND KEHOE
Drywall Nailing 5/11/2020 Partial Approval JENNIFER RABUCHIN
Wood Frame 5/11/2020 Partial Approval JENNIFER RABUCHIN
Insulation 5/12/2020 Partial Approval PIERRE VEGA
Drywall Nailing 5/14/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/7/2020 Partial Approval RAYMOND KEHOE
ELECTRICAL-Final 4/20/2021 Approved DANIEL DREW
Final 4/20/2021 Corrections Issued DANIEL DREW
Footing/Foundation/Slab 4/20/2021 Approved DANIEL DREW
Green Building Final 4/20/2021 Not Ready for Inspection DANIEL DREW
PLUMBING-Final 4/20/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 4/20/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 4/20/2021 Approved DANIEL DREW
Final 11/3/2021 OK to Issue CofO DANIEL DREW
Green Building Final 11/3/2021 Approved DANIEL DREW