10403 W VALLEY SPRING LANE 91602

Certificate Information: 10403 W VALLEY SPRING LANE 91602

Application / Permit
19014-10000-01025
Plan Check / Job No.
B19LA04153
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF EXISTING HOME; SECOND STORY ADDITION 957 SQFT, LOUNGE AND BALCONY
Permit Issued
Issued on 4/30/2019
Issuing Office
Metro
Current Status
CofO Issued on 11/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/28/2019 APPLICANT
Assigned to Plan Check Engineer 3/8/2019 ADAM HEGAZI
Corrections Issued 3/12/2019 ADAM HEGAZI
Green Plans Picked Up 3/15/2019 APPLICANT
Quality Review Completed 3/28/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 4/3/2019 APPLICANT
Plan Check Approved 4/25/2019 ADAM HEGAZI
Issued 4/30/2019 LADBS
CofO in Progress 10/27/2020 THOMAS FINNILA
CofO Issued 11/24/2020 MICHAEL SMITH
Permit Finaled 11/24/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/15/2019 ELENA LOPEZ
Permit Cleared 4/15/2019 ELENA LOPEZ
Sewer availability Cleared 4/15/2019 ELENA LOPEZ
ZI Cleared 4/15/2019 FIPE LEILUA
Green Code Cleared 4/17/2019 COLIN LOREDO
Low Impact Development Cleared 4/25/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 4/25/2019 JEANIE LAM
Trees in Parkway Cleared 4/25/2019 ADRIAN SANCHEZ

Contact Information

Contractor Refined Home Construction Inc; Lic. No.: 1001310-B 8383 WILSHIRE BLVD SUITE 740      BEVERLY HILLS, CA 90211
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/1/2019 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 6/21/2019 Partial Approval RAYMOND KEHOE
Footing/Foundation/Slab 6/28/2019 Approved JEFFREY PARD
BUILDING-Rough-Frame 7/9/2019 Partial Approval JEFFREY PARD
Underground Mechanical 7/9/2019 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/11/2019 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 7/15/2019 Partial Approval RAYMOND KEHOE
Floor/Roof Diaphrgm/Shear Wall 8/6/2019 Partial Approval JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/29/2019 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 9/19/2019 Approved JEFFREY PARD
ELECTRICAL-Rough 10/11/2019 Corrections Issued JEFFREY PARD
HVAC-Rough 10/11/2019 Not Ready for Inspection JEFFREY PARD
Shower Pan 10/11/2019 Approved JEFFREY PARD
Wood Frame 10/11/2019 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 10/18/2019 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 10/18/2019 Partial Approval JEFFREY PARD
PLUMBING-Rough 10/18/2019 Approved JEFFREY PARD
BUILDING-Rough-Frame 11/6/2019 Corrections Issued JEFFREY PARD
Green Building Rough 11/6/2019 Not Ready for Inspection JEFFREY PARD
Pre-Inspection 11/8/2019 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 12/4/2019 Approved JEFFREY PARD
Insulation 12/9/2019 Approved JEFFREY PARD
Drywall Nailing 12/23/2019 Approved JEFFREY PARD
Green Building Rough 12/23/2019 Approved JEFFREY PARD
Interior/Exterior Lathing 1/23/2020 Approved JEFFREY PARD
Shower Pan 1/23/2020 Approved JEFFREY PARD
Gas Test 4/16/2020 Approved PIERRE VEGA
Grounding or Bonding 5/8/2020 Approved JEFFREY PARD
ELECTRICAL-Final 7/17/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 7/21/2020 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 8/17/2020 Corrections Issued THOMAS FINNILA
PLUMBING-Final 8/17/2020 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 8/19/2020 Approved THOMAS FINNILA
PLUMBING-Final 8/19/2020 Approved THOMAS FINNILA
BUILDING-Rough-Frame 8/31/2020 Approved THOMAS FINNILA
Final 8/31/2020 Order to Comply Issued THOMAS FINNILA
Green Building Final 8/31/2020 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 8/31/2020 Approved THOMAS FINNILA
ELECTRICAL-Final 9/3/2020 Approved THOMAS FINNILA
HVAC-Final 9/10/2020 Corrections Issued ARAM AVEDISIAN
PLUMBING-Final 9/10/2020 Approved ARAM AVEDISIAN
Service/Power Release 9/10/2020 Approved ARAM AVEDISIAN
Final 10/19/2020 Partial Inspection THOMAS FINNILA
Green Building Final 10/19/2020 Conditional Approval THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved THOMAS FINNILA
Final 10/27/2020 OK to Issue CofO THOMAS FINNILA
Green Building Final 10/27/2020 Approved THOMAS FINNILA