2133 N MCPHERSON PL 90032

Certificate Information: 2133 N MCPHERSON PL 90032

Application / Permit
19014-10000-00928
Plan Check / Job No.
B19LA03841
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
16'-6" x 10'-0" AND 5'-6" x 18'-0" IRREGULAR SHAPED ADDITION TO (E)DET. GARAGE AND CONVERT INTO A NEW ACCESSORY DWELLING UNIT PER AB 494 & SB 229.
Permit Issued
Issued on 1/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 SARKIS HARABEDIAN
Green Plans Picked Up 6/7/2019 APPLICANT
Corrections Issued 6/12/2019 SARKIS HARABEDIAN
Quality Review Completed 6/24/2019 ABDUL CHEGENI
Building Plans Picked Up 7/15/2019 APPLICANT
Applicant returned to address corrections 10/17/2019 SARKIS HARABEDIAN
Plan Check Approved 12/10/2019 SARKIS HARABEDIAN
Issued 1/6/2020 LADBS
CofO in Progress 4/16/2021 OSVALDO PARAMO
CofO in Progress 4/16/2021 OSVALDO PARAMO
CofO in Progress 4/16/2021 OSVALDO PARAMO
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/25/2019 CELINA MORENO
Grading Pre-Inspection Cleared 9/25/2019 PATRICK MISCHLICH
GPI Written Notices Cleared 10/17/2019 SARKIS HARABEDIAN
Eng Process Fee Ord 176,300 Cleared 10/22/2019 JAMES MORALEZ
Sewer availability Cleared 10/22/2019 JAMES MORALEZ
Green Code Cleared 11/18/2019 NEGAR NEJAD
Hydrant and Access approval Cleared 11/22/2019 JEREMY CARTER
Low Impact Development Cleared 12/5/2019 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 12/5/2019 THOMAS LANG

Contact Information

Engineer Gao,, Jianfeng; Lic. No.: C88478 833 E MOBECK ST APT C      WEST COVINA, CA 91790

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/13/2020 Partial Approval ENRIQUE MIRELES
Footing/Foundation/Slab 7/9/2020 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 7/20/2020 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval COREY HUPP
PLUMBING-Rough 9/21/2020 Approved COREY HUPP
ELECTRICAL-Rough 9/30/2020 Approved COREY HUPP
HVAC-Rough 9/30/2020 Approved COREY HUPP
Sewer 10/22/2020 Approved COREY HUPP
Gas Test 10/27/2020 Partial Approval COREY HUPP
Interior/Exterior Lathing 11/18/2020 Partial Approval COREY HUPP
Insulation 12/1/2020 Approved COREY HUPP
Drywall Nailing 12/14/2020 Not Ready for Inspection COREY HUPP
Green Building Rough 12/14/2020 Approved COREY HUPP
Drywall Nailing 12/24/2020 Approved COREY HUPP
Shower Pan 1/22/2021 Approved COREY HUPP
BUILDING-Rough-Frame 3/17/2021 Approved COREY HUPP
Final 3/17/2021 Corrections Issued COREY HUPP
Green Building Final 3/17/2021 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved COREY HUPP
Smoke Detectors 3/17/2021 Approved COREY HUPP
Final 4/1/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 4/1/2021 Approved OSVALDO PARAMO
Final 4/15/2021 OK to Issue CofO OSVALDO PARAMO