1155 S POINT VIEW ST 90035

Certificate Information: 1155 S POINT VIEW ST 90035

Application / Permit
19014-10000-00858
Plan Check / Job No.
B19LA03576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 27'-0" X 20'-0" ADDITION TO (E) DETACHED GARAGE (16' X 18') AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 AND STORAGE
Permit Issued
Issued on 5/8/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/21/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 MONICA RAMIREZ
Corrections Issued 3/4/2019 DEVIN GORDON
Quality Review Completed 3/7/2019 FELIX FIGUEROA
Green Plans Picked Up 3/8/2019 APPLICANT
Building Plans Picked Up 3/13/2019 APPLICANT
Plan Check Approved 5/7/2019 MONICA RAMIREZ
Issued 5/8/2019 LADBS
CofO in Progress 8/21/2020 MATTHEW NUCKOLLS
No Progress 9/4/2020 ELMER BLAND
CofO in Progress 9/24/2020 ELMER BLAND
Permit Finaled 9/24/2020 DEROLD HAUFF
CofO Issued 9/24/2020 DEROLD HAUFF
Permit Finaled 9/24/2020 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 3/6/2019 MARTIN FRAGOSO
Address approval Cleared 4/1/2019 ERIK BEASLEY
CPC Cleared 4/1/2019 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 4/1/2019 ERIK BEASLEY
Green Code Cleared 4/1/2019 SARAH ABOULHOSN
Roof/Waste drainage to street Cleared 4/1/2019 ERIK BEASLEY
Sewer availability Cleared 4/1/2019 ERIK BEASLEY
HPOZ Cleared 5/3/2019 JONATHAN KAPLAN

Contact Information

Contractor Elden Development Construction Inc; Lic. No.: 970717-B 3400 WEST 6TH STREET SUITE 314      LOS ANGELES, CA 90020
Engineer Kim,, Hosang; Lic. No.: C67288 10632 BALCOM AVE      GRANADA HILLS, CA 91344

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 6/20/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 6/20/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 6/20/2019 Approved KATHRYN BUTTERWORTH
METHANE-Rough 6/26/2019 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 6/28/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 6/28/2019 Partial Approval RICHARD STEINBACH
Wood Frame 7/24/2019 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 9/6/2019 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 9/6/2019 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 9/19/2019 Not Ready for Inspection ELMER BLAND
Green Building Rough 9/19/2019 Not Ready for Inspection ELMER BLAND
Wood Frame 9/19/2019 Not Ready for Inspection ELMER BLAND
BUILDING-Rough-Frame 9/26/2019 Approved KATHRYN BUTTERWORTH
Green Building Rough 9/26/2019 Approved KATHRYN BUTTERWORTH
Special/Order Compliance 9/26/2019 Approved CHRISTOPHER DELLEFIELD
Wood Frame 9/26/2019 Approved KATHRYN BUTTERWORTH
Insulation 10/16/2019 Approved KATHRYN BUTTERWORTH
Drywall Nailing 10/23/2019 Approved HENRY KIM
Interior/Exterior Lathing 11/5/2019 Corrections Issued ROBERT VORHIS
Interior/Exterior Lathing 11/20/2019 Partial Approval KATHRYN BUTTERWORTH
Wood Frame 11/20/2019 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/14/2020 Approved MATTHEW NUCKOLLS
Final 2/14/2020 Conditional Approval MATTHEW NUCKOLLS
Footing/Foundation/Slab 2/14/2020 Approved MATTHEW NUCKOLLS
Green Building Final 2/14/2020 Approved MATTHEW NUCKOLLS
HVAC-Final 2/14/2020 Approved MATTHEW NUCKOLLS
PLUMBING-Final 2/14/2020 Approved MATTHEW NUCKOLLS
SGSOV-Seismic Gas S/O Valve 2/14/2020 SGSOV Approved MATTHEW NUCKOLLS
Service/Power Release 2/14/2020 Approved MATTHEW NUCKOLLS
Smoke Detectors 2/14/2020 Approved MATTHEW NUCKOLLS
Final 8/21/2020 OK to Issue CofO MATTHEW NUCKOLLS