450 N MCCADDEN PL 90004
Certificate Information: 450 N MCCADDEN PL 90004
- Application / Permit
- 19014-10000-00760
- Plan Check / Job No.
- B19LA03161
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PARTIAL REMOVAL OF REAR PORTION OF BUILDING. REMODEL AND TWO-STORY ADDITION.
- Permit Issued
- Issued on 10/22/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2019 | JOE VO |
| Corrections Issued | 2/27/2019 | JOE VO |
| Quality Review Completed | 3/1/2019 | GARO TELMI |
| Building Plans Picked Up | 3/1/2019 | APPLICANT |
| Green Plans Picked Up | 3/4/2019 | APPLICANT |
| Applicant returned to address corrections | 3/20/2019 | JOE VO |
| Applicant returned to address corrections | 4/25/2019 | JOE VO |
| Plan Check Approved | 5/16/2019 | JOE VO |
| No Progress | 7/1/2019 | JOE VO |
| Plan Check Approved | 7/29/2019 | JOE VO |
| Issued | 10/22/2019 | LADBS |
| CofO in Progress | 3/29/2025 | RONNIE MINDANAO |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
| CofO Issued | 4/19/2025 | DEROLD HAUFF |
| Permit Finaled | 4/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Abandoned oil well | Cleared | 3/8/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2019 | JEANETTE VONG |
| ZI | Cleared | 3/28/2019 | SUKI GERSHENHORN |
| CPC | Cleared | 7/11/2019 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 7/15/2019 | KHEDER ALRAZAA |
| HPOZ | Cleared | 7/15/2019 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 7/15/2019 | SUKI GERSHENHORN |
| Sewer availability | Cleared | 7/19/2019 | ADRIAN SANCHEZ |
| Low Impact Development | Cleared | 7/29/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 7/29/2019 | ERIK BEASLEY |
Contact Information
| Contractor | C C & E Companies; Lic. No.: 999877-B | 1828 S WESTERN AVE #101 LOS ANGELES, CA 90006 |
| Engineer | Varela, Olivas, Benjamin; Lic. No.: S5714 | 12831 PANAMA STREET LOS ANGELES, CA 90066 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/3/2019 | Partial Inspection | DANIEL GONZALEZ |
| Deputy Drilled-In Anchors | 12/10/2019 | Partial Approval | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 12/11/2019 | No Access for Inspection | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 12/16/2019 | No Access for Inspection | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 12/17/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 12/17/2019 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Rough | 12/17/2019 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 12/19/2019 | No Access for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 12/20/2019 | Partial Approval | DANIEL GONZALEZ |
| METHANE-Barrier | 12/20/2019 | Not Ready for Inspection | DANIEL GONZALEZ |
| METHANE-Subgrade | 12/20/2019 | Not Ready for Inspection | DANIEL GONZALEZ |
| METHANE-Rough | 1/10/2020 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 1/10/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 1/16/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 1/17/2020 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 1/21/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Reinf. Concrete | 1/23/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 1/28/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 6/17/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/10/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/13/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/23/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Rough | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| Rough-Elec/Plmb/HVAC | 7/23/2020 | Partial Approval | ARTHUR SARGSYAN |
| PLUMBING-Rough | 7/28/2020 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 7/31/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Wood Frame | 7/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 8/4/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 8/6/2020 | Approved | ARTHUR SARGSYAN |
| Insulation | 8/12/2020 | Corrections Issued | THOMAS LOGRASSO |
| Wood Frame | 8/14/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 8/28/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 9/1/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 9/9/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 9/9/2020 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 9/16/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 9/16/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 9/23/2020 | Approved | ARTHUR SARGSYAN |
| Special/Order Compliance | 10/29/2020 | Corrections Issued | JOSEPH MCGARRY |
| Special/Order Compliance | 11/6/2020 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 11/18/2020 | Partial Approval | SCOTT FINNILA |
| Deputy Shotcrete | 12/4/2020 | No Access for Inspection | ELMER BLAND |
| Interior/Exterior Lathing | 12/18/2020 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 12/18/2020 | Corrections Issued | STUART CHAPMAN |
| Shower Pan | 12/21/2020 | Approved | SCOTT FINNILA |
| Interior/Exterior Lathing | 1/8/2021 | Partial Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 4/12/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/12/2021 | Partial Approval | JOSEPH MCGARRY |
| Service/Power Release | 6/11/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| METHANE-Final | 7/21/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/22/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/23/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Final | 9/23/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 10/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Not Required | ARTHUR SARGSYAN |
| Smoke Detectors | 10/1/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 10/6/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Barrier | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| METHANE-Subgrade | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Smoke Detectors | 10/28/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/24/2022 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/24/2022 | Approved | ARTHUR SARGSYAN |
| Special/Order Compliance | 2/5/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 2/19/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 3/24/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 3/27/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 3/28/2025 | OK to Issue CofO | RONNIE MINDANAO |