14629 W GREENLEAF ST 91403
Certificate Information: 14629 W GREENLEAF ST 91403
- Application / Permit
- 19014-10000-00689
- Plan Check / Job No.
- B19LA02805
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-STORY ADDITION & MAJOR REMODEL TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- CofO Issued on 8/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 3/1/2019 | YAQUB MIRZA |
| Corrections Issued | 3/1/2019 | YAQUB MIRZA |
| Quality Review Completed | 3/15/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 3/22/2019 | APPLICANT |
| Green Plans Picked Up | 3/22/2019 | APPLICANT |
| Applicant returned to address corrections | 6/10/2021 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 7/30/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 10/13/2021 | NILOOFAR MEHRAIN |
| Issued | 3/18/2022 | APPLICANT |
| CofO in Progress | 7/31/2023 | MISAEL ESPARZA |
| Permit Finaled | 8/28/2023 | RUBEN SALAS |
| CofO Issued | 8/28/2023 | RUBEN SALAS |
| Permit Finaled | 8/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Hold | Cleared | 3/26/2019 | LOURDES RAMIRO |
| Permit | Cleared | 8/4/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 8/11/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 8/11/2020 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 1/13/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Grading Pre-Inspection | Cleared | 7/30/2021 | YAQUB MIRZA |
| Green Code | Cleared | 7/30/2021 | SARAH ABOULHOSN |
Contact Information
| Contractor | B & R Creative Builders Inc; Lic. No.: 969864-B | 6820 LA TIJERA BLVD STE 111 LOS ANGELES, CA 90045 |
| Engineer | Velasco,, Jose Luis; Lic. No.: C76091 | 8371 BENJAMIN DR HUNTINGTON BEACH, CA 92647 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/31/2022 | Approved | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/22/2022 | Approved | MATT KELLERMAN |
| BUILDING-Rough-Frame | 8/2/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 8/2/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 8/3/2022 | Partial Approval | CALEB MEISTER |
| Insulation | 8/3/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 10/18/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 10/18/2022 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 10/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2022 | Partial Approval | MISAEL ESPARZA |
| HVAC-Rough | 10/25/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/25/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/27/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 10/27/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/27/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 10/27/2022 | Partial Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/2/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 11/2/2022 | Conditional Approval | MISAEL ESPARZA |
| Insulation | 11/21/2022 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/21/2022 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 12/7/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 12/7/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 12/15/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/9/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 6/9/2023 | Corrections Issued | JOHN COLEMAN |
| Gas Test | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Final | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 6/9/2023 | Approved | JOHN COLEMAN |
| HVAC-Final | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Final | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 6/9/2023 | SGSOV Not Ready | JOHN COLEMAN |
| Service/Power Release | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Smoke Detectors | 6/9/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 6/26/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 6/26/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 6/26/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 6/26/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 7/11/2023 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Final | 7/11/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 7/11/2023 | Approved | JACK KARGODORIAN |
| Service/Power Release | 7/11/2023 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 7/28/2023 | Approved | MISAEL ESPARZA |
| Final | 7/28/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 7/28/2023 | Approved | MISAEL ESPARZA |