1100 1/2 W 68TH ST 90044

Certificate Information: 1100 1/2 W 68TH ST 90044

Application / Permit
19014-10000-00610
Plan Check / Job No.
B19LA02513
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 227 SQ FT OF (E) 2-CAR GARAGE TO (N) ADU. ADD 218 SQ FT SECOND FLOOR TO (N) ADU. REMODEL (E) 2-CAR GARAGE AND ROOF
Permit Issued
Issued on 3/26/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/1/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/6/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 JOE VO
Corrections Issued 2/20/2019 JOE VO
Quality Review Completed 2/22/2019 GARO TELMI
Building Plans Picked Up 2/25/2019 APPLICANT
Green Plans Picked Up 2/28/2019 APPLICANT
Plan Check Approved 3/26/2019 JOE VO
Issued 3/26/2019 LADBS
CofO in Progress 9/4/2020 FREDDIE RIVERA
Permit Finaled 10/1/2020 DEROLD HAUFF
Permit Finaled 10/1/2020 DEROLD HAUFF
CofO Issued 10/1/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/28/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 2/28/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/5/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 3/5/2019 ROBERT DUFF
Sewer availability Cleared 3/5/2019 ELENA LOPEZ
Green Code Cleared 3/11/2019 JOE VO

Contact Information

Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2019 Corrections Issued FREDDIE RIVERA
Deputy Drilled-In Anchors 4/17/2019 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 4/19/2019 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 4/24/2019 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 4/24/2019 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/7/2019 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/21/2019 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 6/14/2019 No Access for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/14/2019 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 6/20/2019 Conditional Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/20/2019 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 6/20/2019 Approved FREDDIE RIVERA
PLUMBING-Rough 7/12/2019 Approved FREDDIE RIVERA
ELECTRICAL-Rough 9/6/2019 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/6/2019 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/31/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/31/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 1/31/2020 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 2/26/2020 Partial Approval HORACE FULTZ
Green Building Rough 2/26/2020 Approved HORACE FULTZ
BUILDING-Rough-Frame 3/5/2020 Approved FREDDIE RIVERA
Insulation 3/5/2020 Conditional Approval FREDDIE RIVERA
Drywall Nailing 3/13/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/18/2020 Approved FREDDIE RIVERA
Shower Pan 3/18/2020 Approved FREDDIE RIVERA
Final 6/25/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 6/25/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/25/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 6/25/2020 Approved FREDDIE RIVERA
Sewer 7/20/2020 Approved HAMIK HARTOUNIAN
Final 7/30/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 7/30/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/30/2020 SGSOV Not Ready FREDDIE RIVERA
Final 8/12/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 8/12/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Not Ready FREDDIE RIVERA
Final 8/20/2020 Conditional Approval FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/20/2020 SGSOV Approved FREDDIE RIVERA