5196 W ORANGE PL 90008

Certificate Information: 5196 W ORANGE PL 90008

Application / Permit
19014-10000-00558
Plan Check / Job No.
B19LA02310
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FOR PROPOSED 1ST & 2ND FLOOR ADDITION + MAJOR INTERIOR REMODEL TO (E) SFD.
Permit Issued
Issued on 7/2/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2019 APPLICANT
Assigned to Plan Check Engineer 2/28/2019 SERGIO GUTIERREZ
Corrections Issued 3/14/2019 SERGIO GUTIERREZ
Quality Review Completed 3/19/2019 ARMEN JIVALAGIAN
Plan Check Approved 6/11/2019 SERGIO GUTIERREZ
Issued 7/2/2019 LADBS
Green Plans Picked Up 10/14/2020 APPLICANT
Building Plans Picked Up 2/9/2022 APPLICANT
CofO in Progress 6/21/2024 ANTHONY EGSON
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/8/2019 ELENA LOPEZ
Grading Pre-Inspection Cleared 4/8/2019 PATRICK MISCHLICH
Hydrant and Access approval Cleared 4/8/2019 GILBERT URREA
Sewer availability Cleared 4/8/2019 ELENA LOPEZ
ZA Case Cleared 4/8/2019 ANNA VAN
Low Impact Development Cleared 5/28/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/31/2019 ADRIAN SANCHEZ
GPI Written Notices Cleared 6/11/2019 SERGIO GUTIERREZ
Green Code Cleared 6/11/2019 SARAH ABOULHOSN

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/26/2019 Approved COREY HUPP
Footing/Foundation/Slab 5/6/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 5/7/2020 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 5/15/2020 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 10/26/2020 Not Ready for Inspection DONALD CRICHLOW
Footing/Foundation/Slab 11/4/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 12/21/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 12/28/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/8/2022 Corrections Issued CRAIG DAVIS
Drywall Nailing 3/17/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/17/2022 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/23/2022 Corrections Issued ANTHONY EGSON
Drywall Nailing 4/6/2022 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Not Ready for Inspection ANTHONY EGSON
Wood Frame 4/6/2022 Corrections Issued ANTHONY EGSON
Deputy Wood Construction 7/12/2022 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 7/12/2022 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 7/13/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 7/13/2022 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 7/13/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 7/13/2022 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 7/13/2022 Approved ANTHONY EGSON
Special/Order Compliance 7/27/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/3/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Corrections Issued ANTHONY EGSON
Green Building Rough 8/3/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 8/3/2022 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 8/23/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/23/2022 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Approved ANTHONY EGSON
Green Building Rough 8/23/2022 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 8/23/2022 Not Ready for Inspection ANTHONY EGSON
Wood Frame 8/23/2022 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 9/6/2022 Approved ANTHONY EGSON
HVAC-Rough 9/6/2022 Approved ANTHONY EGSON
HVAC-Rough 9/21/2022 Approved ANTHONY EGSON
Green Building Rough 10/6/2022 Approved ANTHONY EGSON
Interior/Exterior Lathing 11/2/2022 Corrections Issued ANTHONY EGSON
Interior/Exterior Lathing 12/29/2022 No Access for Inspection ANTHONY EGSON
Interior/Exterior Lathing 1/9/2023 No Access for Inspection ANTHONY EGSON
Interior/Exterior Lathing 1/19/2023 Not Ready for Inspection ANTHONY EGSON
Shower Pan 1/19/2023 Approved ANTHONY EGSON
Sewer 2/22/2023 Not Ready for Inspection ANTHONY EGSON
Underground Mechanical 2/22/2023 Not Ready for Inspection ANTHONY EGSON
Sewer 3/7/2023 Approved ANTHONY EGSON
Underground Mechanical 3/7/2023 Approved ANTHONY EGSON
Insulation 4/24/2023 Approved ANTHONY EGSON
Drywall Nailing 5/3/2023 Approved ANTHONY EGSON
ELECTRICAL-Final 2/21/2024 Partial Approval ANTHONY EGSON
HVAC-Final 2/21/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 2/21/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Final 3/14/2024 Corrections Issued ANTHONY EGSON
HVAC-Final 3/14/2024 Approved ANTHONY EGSON
PLUMBING-Final 3/14/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 3/20/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 3/22/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 3/27/2024 Approved ALIZAH MAYAGOITIA
Service/Power Release 3/27/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 6/20/2024 Approved ANTHONY EGSON
Final 6/20/2024 OK to Issue CofO ANTHONY EGSON
Footing/Foundation/Slab 6/20/2024 Approved ANTHONY EGSON
Green Building Final 6/20/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Approved ANTHONY EGSON
Service/Power Release 6/20/2024 Approved ANTHONY EGSON
Smoke Detectors 6/20/2024 Approved ANTHONY EGSON