1371 N TOWER GROVE DR 90210
Certificate Information: 1371 N TOWER GROVE DR 90210
- Application / Permit
- 19014-10000-00528
- Plan Check / Job No.
- B19LA02177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental to 16014-10000-02977: Revise Architectural and Structural Plans. No change to Height, Floor Area or Overall Dimension
- Permit Issued
- Issued on 5/2/2019
- Issuing Office
- Metro
- Current Status
- Issued on 5/2/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/28/2019 | YAQUB MIRZA |
| Corrections Issued | 3/7/2019 | YAQUB MIRZA |
| Quality Review Completed | 3/15/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 3/18/2019 | APPLICANT |
| Applicant returned to address corrections | 3/21/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 3/27/2019 | APPLICANT |
| Plan Check Approved | 5/2/2019 | HERNAN ARREOLA |
| Issued | 5/2/2019 | LADBS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 4/3/2019 | MITESH PATEL |
| Green Code | Cleared | 4/4/2019 | KHEDER ALRAZAA |
| GPI Written Notices | Cleared | 5/2/2019 | YAQUB MIRZA |
| Grading Pre-Inspection | Cleared | 5/2/2019 | YAQUB MIRZA |
Contact Information
| Architect | Mahmoodi,, Arshia; Lic. No.: C34875 | 6543 FRANKLIN AVENUE # 306 LOS ANGELES, CA 90028 |
| Engineer | Gorgy,, Moheb Shohdy; Lic. No.: C53260 | 1545 VICTORY BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/27/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 3/25/2020 | Partial Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 3/25/2020 | Partial Approval | CARLOS MATAMOROS |
| Special/Order Compliance | 3/25/2020 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 3/26/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 10/2/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 10/2/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Green Building Rough | 10/8/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Special/Order Compliance | 10/8/2020 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Rough | 10/23/2020 | Partial Approval | ANTHONY MCDOWALL |
| Sewer | 10/23/2020 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 10/28/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 10/28/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 10/28/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 10/28/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 10/29/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 10/29/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Underground Mechanical | 10/29/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 11/2/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 11/2/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 11/2/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 11/12/2020 | Corrections Issued | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 11/17/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Steel/Welding | 1/13/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 2/4/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Wood Frame | 2/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 5/2/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |