1226 W 50TH ST 90037

Certificate Information: 1226 W 50TH ST 90037

Application / Permit
19014-10000-00350
Plan Check / Job No.
B19LA01428
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (E) HOUSE 1,409 SF ENTIRELY, CONVERTING 3 BED/1 BATH INTO 5 BEDROOMS/2 BATHS. (N) DRIVEWAY APPROACH. "COMPLY WITH DEPARTMENT ORDER effective date 11/05/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 832508.
Permit Issued
Issued on 6/4/2020
Issuing Office
Current Status
Permit Finaled on 12/16/2020

Permit Application Status History

Submitted 1/23/2019 APPLICANT
Assigned to Plan Check Engineer 2/14/2019 ADAM HEGAZI
Corrections Issued 2/19/2019 ADAM HEGAZI
Quality Review Completed 2/20/2019 MOHAMMAD FIROUZBAKHT
Building Plans Picked Up 3/15/2019 APPLICANT
Green Plans Picked Up 3/15/2019 APPLICANT
Plan Check Approved 10/25/2019 ADAM HEGAZI
Issued 6/4/2020 APPLICANT
Permit Finaled 12/15/2020 MARIO CUEVAS

Permit Application Clearance Information

Permit Cleared 3/15/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/18/2019 ELAINE LEI
Sewer availability Cleared 3/18/2019 ELAINE LEI
Trees in Parkway Cleared 3/18/2019 ADRIAN SANCHEZ
Community Plan Implem. Overlay Cleared 10/4/2019 HELEN JADALI
Green Code Cleared 10/7/2019 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 10/24/2019 THOMAS LANG

Contact Information

Contractor M & M Design And Construction; Lic. No.: 1038932-B 2851 W 120TH ST STE #E112      HAWTHORNE, CA 90250
Engineer Kwei,, Peter; Lic. No.: C72100 13104 GLEN COURT UNIT 52      CHINO HILLS, CA 91748

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/1/2020 Approved MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 7/14/2020 Corrections Issued MARIO CUEVAS
Footing/Foundation/Slab 7/14/2020 Approved MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Approved MARIO CUEVAS
Insulation 8/31/2020 No Access for Inspection MARIO CUEVAS
Insulation 9/1/2020 Approved MARIO CUEVAS
Drywall Nailing 9/4/2020 Approved MEL KHACHATOURIAN
Final 12/15/2020 Permit Finaled MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 12/15/2020 SGSOV Approved MARIO CUEVAS
Smoke Detectors 12/15/2020 Approved MARIO CUEVAS
Wood Frame 12/15/2020 Approved MARIO CUEVAS