1536 W 92ND ST 90047

Certificate Information: 1536 W 92ND ST 90047

Application / Permit
19014-10000-00342
Plan Check / Job No.
B19LA01390
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of (E) garage 18' x 16' into Accessory Dwelling Unit with new addition of 18' x 29' per LAMC 12.22 A.33(c) and (d). All work per engineering.
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 12/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2019 HELEN NGUYEN
Corrections Issued 1/23/2019 HELEN NGUYEN
Applicant returned to address corrections 2/22/2021 LUKE GONZALES
Applicant returned to address corrections 8/4/2021 LUISANGEL VALENZUELA
Plan Check Approved 8/10/2021 JENNIFER LEE
Issued 8/24/2021 APPLICANT
Building Plans Picked Up 8/30/2021 APPLICANT
CofO in Progress 12/4/2025 SALVADOR MARTINEZ
Permit Finaled 12/6/2025 DEROLD HAUFF
CofO Issued 12/6/2025 DEROLD HAUFF
Permit Finaled 12/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction within easement Cleared 6/14/2019 RIDWAN HARDY
Address approval Cleared 8/17/2020 RENZ SORIANO
Address approval Cleared 8/17/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/17/2020 RENZ SORIANO
Sewer availability Cleared 8/17/2020 RENZ SORIANO
ZI Cleared 8/17/2020 HELEN JADALI
Low Impact Development Cleared 12/9/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/9/2020 RENZ SORIANO

Contact Information

Contractor Owner-Builder       ,
Engineer Manlangit,, Vicente Balingasa; Lic. No.: C75499 7919 SAUSALITO AVE      WEST HILLS, CA 91304

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/11/2022 Approved FREDDIE RIVERA
Pre-Inspection 12/5/2022 Approved ENRIQUE MIRELES
Underground Mechanical 12/28/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 1/30/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/6/2023 Corrections Issued ENRIQUE MIRELES
Pre-Inspection 2/9/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Approved ENRIQUE MIRELES
Green Building Rough 3/17/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/23/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/23/2023 Approved ENRIQUE MIRELES
HVAC-Rough 3/23/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 3/23/2023 Approved ENRIQUE MIRELES
Insulation 3/29/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 3/29/2023 Not Ready for Inspection ENRIQUE MIRELES
Shower Pan 3/29/2023 Not Ready for Inspection ENRIQUE MIRELES
Drywall Nailing 4/7/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 4/7/2023 Approved ENRIQUE MIRELES
Shower Pan 4/7/2023 Approved ENRIQUE MIRELES
Sewer 4/25/2023 Approved ENRIQUE MIRELES
Underground Mechanical 5/16/2023 Approved ENRIQUE MIRELES
Final 9/1/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 9/1/2023 Approved ENRIQUE MIRELES
Green Building Final 9/1/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 9/1/2023 Approved ENRIQUE MIRELES
Service/Power Release 9/29/2023 Approved ENRIQUE MIRELES
Final 9/3/2025 Corrections Issued SALVADOR MARTINEZ
Final 10/6/2025 Corrections Issued SALVADOR MARTINEZ
Final 10/17/2025 OK to Issue CofO SALVADOR MARTINEZ