2637 N WESTRIDGE ROAD 90049

Certificate Information: 2637 N WESTRIDGE ROAD 90049

Application / Permit
19014-10000-00302
Plan Check / Job No.
B19LA01266
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW OCCUPIED DECK IN REAR LOT
Permit Issued
Issued on 3/27/2019
Issuing Office
Metro
Current Status
Issued on 3/27/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/22/2019 APPLICANT
Assigned to Plan Check Engineer 2/7/2019 ROSENDO MEDINA
Corrections Issued 2/11/2019 ROSENDO MEDINA
Quality Review Completed 2/13/2019 MOHAMMAD FIROUZBAKHT
Plan Check Approved 3/27/2019 ROSENDO MEDINA
Issued 3/27/2019 LADBS

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/26/2019 KARAN PATEL
Eng Process Fee Ord 176,300 Cleared 3/26/2019 KARAN PATEL
Grading Pre-Inspection Cleared 3/26/2019 BARTON HOLMES
Low Impact Development Cleared 3/26/2019 JORGE MEJIA LEMUS
BHO/Hillside ordinance Cleared 3/27/2019 JOSE CRUZ RODRIGUEZ
BHO/Hillside ordinance Cleared 3/27/2019 JOSE CRUZ RODRIGUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/21/2019 Corrections Issued TIM CHRISTENSEN
Footing/Foundation/Slab 8/8/2019 Not Ready for Inspection DAVID FEILER
Piling/Pier/Caisson 8/14/2019 Approved DAVID FEILER
Deputy Reinf. Concrete 10/2/2019 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 12/3/2019 Corrections Issued DAVID FEILER
FLOOD-Proofing Certificate 12/3/2019 Approved DAVID FEILER
Final 12/3/2019 Not Ready for Inspection DAVID FEILER
Footing/Foundation/Slab 12/3/2019 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 12/3/2019 SGSOV Not Ready DAVID FEILER
Smoke Detectors 12/3/2019 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 12/18/2019 Partial Approval DAVID FEILER
Wood Frame 12/24/2019 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 2/18/2020 Corrections Issued TIM CHRISTENSEN
Pre-Inspection 4/23/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/7/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/8/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Final 6/8/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/8/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 6/8/2020 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 6/8/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 7/22/2020 Partial Approval TIM CHRISTENSEN
BUILDING-Rough-Frame 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
Deck 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Final 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
Final 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 6/8/2021 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 6/8/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 2/9/2022 Approved JUAN VALENZUELA
Final 2/9/2022 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 2/9/2022 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 2/9/2022 Approved JUAN VALENZUELA
Final 3/7/2024 Conditional Approval KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved KENNETH NAGLE