1237 N COMMONWEALTH AVE 90029
Certificate Information: 1237 N COMMONWEALTH AVE 90029
- Application / Permit
- 19014-10000-00217
- Plan Check / Job No.
- B19LA00895
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE INTO A.D.U. AND ADDITION PER AB-494 AND SB-229 "COMPLY WITH DEPARTMENT ORDER effective date 07/19/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 4/22/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/16/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2019 | APPLICANT |
| Green Plans Picked Up | 1/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 2/4/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 2/5/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 2/6/2019 | APPLICANT |
| Applicant returned to address corrections | 2/20/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 4/10/2019 | EMMANUEL MARTINEZ |
| Issued | 4/22/2019 | LADBS |
| CofO in Progress | 2/7/2020 | PATRICK QUALEY |
| CofO in Progress | 2/27/2020 | PATRICK QUALEY |
| CofO Issued | 3/16/2020 | JEFF NAPIER |
| Permit Finaled | 3/16/2020 | JEFF NAPIER |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2019 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 2/20/2019 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 2/20/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/20/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 2/20/2019 | JEANETTE VONG |
| ZI | Cleared | 2/20/2019 | ANNA VAN |
| Hydrant and Access approval | Cleared | 2/22/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 4/3/2019 | ELENA LOPEZ |
| GPI Written Notices | Cleared | 4/10/2019 | EMMANUEL MARTINEZ |
| Green Code | Cleared | 4/17/2019 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2019 | No Violation (special insp) | PATRICK QUALEY |
| Footing/Foundation/Slab | 4/26/2019 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 5/28/2019 | Partial Inspection | PATRICK QUALEY |
| Deputy Drilled-In Anchors | 6/5/2019 | Approved | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 6/6/2019 | Corrections Issued | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 6/7/2019 | Partial Approval | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 6/20/2019 | Corrections Issued | PATRICK QUALEY |
| Excavation/Setback/Form/Re-Bar | 6/25/2019 | Approved | PATRICK QUALEY |
| ELECTRICAL-Rough | 7/1/2019 | Approved | PATRICK QUALEY |
| Pre-Inspection | 8/29/2019 | Approved | PATRICK QUALEY |
| Special/Order Compliance | 9/17/2019 | Not Ready for Inspection | PATRICK QUALEY |
| Sewer | 9/25/2019 | Not Ready for Inspection | PATRICK QUALEY |
| Special/Order Compliance | 10/9/2019 | Partial Inspection | TIMOTHY MCCURDY |
| Pre-Inspection | 10/16/2019 | Not Ready for Inspection | PATRICK QUALEY |
| Drywall Nailing | 10/21/2019 | Approved | PATRICK QUALEY |
| Insulation | 10/21/2019 | Approved | PATRICK QUALEY |
| BUILDING-Rough-Frame | 10/28/2019 | Approved | PATRICK QUALEY |
| Final | 10/28/2019 | Corrections Issued | PATRICK QUALEY |
| Footing/Foundation/Slab | 10/28/2019 | Approved | PATRICK QUALEY |
| Green Building Final | 10/28/2019 | Not Ready for Inspection | PATRICK QUALEY |
| Green Building Rough | 10/28/2019 | Approved | PATRICK QUALEY |
| PLUMBING-Final | 10/28/2019 | Corrections Issued | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 10/28/2019 | SGSOV Approved | PATRICK QUALEY |
| Smoke Detectors | 10/28/2019 | Approved | PATRICK QUALEY |
| Final | 11/4/2019 | Corrections Issued | PATRICK QUALEY |
| Green Building Final | 11/4/2019 | Not Ready for Inspection | PATRICK QUALEY |
| Final | 2/6/2020 | OK to Issue CofO | PATRICK QUALEY |
| Green Building Final | 2/6/2020 | Approved | PATRICK QUALEY |