1237 N COMMONWEALTH AVE 90029

Certificate Information: 1237 N COMMONWEALTH AVE 90029

Application / Permit
19014-10000-00217
Plan Check / Job No.
B19LA00895
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE INTO A.D.U. AND ADDITION PER AB-494 AND SB-229 "COMPLY WITH DEPARTMENT ORDER effective date 07/19/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/22/2019
Issuing Office
Metro
Current Status
CofO Issued on 3/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2019 APPLICANT
Green Plans Picked Up 1/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 EMMANUEL MARTINEZ
Corrections Issued 2/4/2019 EMMANUEL MARTINEZ
Quality Review Completed 2/5/2019 MOHAMMAD FIROUZBAKHT
Building Plans Picked Up 2/6/2019 APPLICANT
Applicant returned to address corrections 2/20/2019 EMMANUEL MARTINEZ
Plan Check Approved 4/10/2019 EMMANUEL MARTINEZ
Issued 4/22/2019 LADBS
CofO in Progress 2/7/2020 PATRICK QUALEY
CofO in Progress 2/27/2020 PATRICK QUALEY
CofO Issued 3/16/2020 JEFF NAPIER
Permit Finaled 3/16/2020 JEFF NAPIER

Permit Application Clearance Information

Address approval Cleared 2/20/2019 JEANETTE VONG
Grading Pre-Inspection Cleared 2/20/2019 PATRICK MISCHLICH
Low Impact Development Cleared 2/20/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/20/2019 JEANETTE VONG
Sewer availability Cleared 2/20/2019 JEANETTE VONG
ZI Cleared 2/20/2019 ANNA VAN
Hydrant and Access approval Cleared 2/22/2019 GEORGE SUCHAND
Eng Process Fee Ord 176,300 Cleared 4/3/2019 ELENA LOPEZ
GPI Written Notices Cleared 4/10/2019 EMMANUEL MARTINEZ
Green Code Cleared 4/17/2019 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/24/2019 No Violation (special insp) PATRICK QUALEY
Footing/Foundation/Slab 4/26/2019 Corrections Issued PATRICK QUALEY
Footing/Foundation/Slab 5/28/2019 Partial Inspection PATRICK QUALEY
Deputy Drilled-In Anchors 6/5/2019 Approved PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 6/6/2019 Corrections Issued PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 6/7/2019 Partial Approval PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 6/20/2019 Corrections Issued PATRICK QUALEY
Excavation/Setback/Form/Re-Bar 6/25/2019 Approved PATRICK QUALEY
ELECTRICAL-Rough 7/1/2019 Approved PATRICK QUALEY
Pre-Inspection 8/29/2019 Approved PATRICK QUALEY
Special/Order Compliance 9/17/2019 Not Ready for Inspection PATRICK QUALEY
Sewer 9/25/2019 Not Ready for Inspection PATRICK QUALEY
Special/Order Compliance 10/9/2019 Partial Inspection TIMOTHY MCCURDY
Pre-Inspection 10/16/2019 Not Ready for Inspection PATRICK QUALEY
Drywall Nailing 10/21/2019 Approved PATRICK QUALEY
Insulation 10/21/2019 Approved PATRICK QUALEY
BUILDING-Rough-Frame 10/28/2019 Approved PATRICK QUALEY
Final 10/28/2019 Corrections Issued PATRICK QUALEY
Footing/Foundation/Slab 10/28/2019 Approved PATRICK QUALEY
Green Building Final 10/28/2019 Not Ready for Inspection PATRICK QUALEY
Green Building Rough 10/28/2019 Approved PATRICK QUALEY
PLUMBING-Final 10/28/2019 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 10/28/2019 SGSOV Approved PATRICK QUALEY
Smoke Detectors 10/28/2019 Approved PATRICK QUALEY
Final 11/4/2019 Corrections Issued PATRICK QUALEY
Green Building Final 11/4/2019 Not Ready for Inspection PATRICK QUALEY
Final 2/6/2020 OK to Issue CofO PATRICK QUALEY
Green Building Final 2/6/2020 Approved PATRICK QUALEY