2204-2206 W AYR ST 90039
Certificate Information: 2204-2206 W AYR ST 90039
- Application / Permit
- 19014-10000-00154
- Plan Check / Job No.
- B19LA00666
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REAR DWELLING UNIT WILL BE REMODELED AND 2ND FLOOR ADDITION 1682 SF.
- Permit Issued
- Issued on 8/26/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 2/13/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/15/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 2/20/2019 | APPLICANT |
| Green Plans Picked Up | 3/6/2019 | APPLICANT |
| Applicant returned to address corrections | 5/29/2019 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 6/20/2019 | SERGIO GUTIERREZ |
| Plan Check Approved | 7/1/2019 | SERGIO GUTIERREZ |
| Issued | 8/26/2019 | LADBS |
| CofO in Progress | 12/7/2021 | THOMAS LOGRASSO |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
| CofO Issued | 1/8/2022 | DEROLD HAUFF |
| Permit Finaled | 1/8/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2019 | CELINA MORENO |
| Green Code | Cleared | 5/15/2019 | SERGIO GUTIERREZ |
| Sewer availability | Cleared | 5/15/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 5/16/2019 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 6/19/2019 | SERGIO GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 6/27/2019 | ELENA LOPEZ |
| GPI Written Notices | Cleared | 7/1/2019 | SERGIO GUTIERREZ |
| Grading Pre-Inspection | Cleared | 7/1/2019 | SERGIO GUTIERREZ |
Contact Information
| Architect | Bestor,, Barbara A; Lic. No.: C26132 | 2030 HYPERION AVENUE LOS ANGELES, CA 90027 |
| Contractor | A Clas Builders & Design Inc; Lic. No.: 770974-B | 7050 OWENSMOUTH AVENUE STE 208 CANOGA PARK, CA 91303 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/13/2019 | Corrections Issued | AJA COLLAY |
| Footing/Foundation/Slab | 12/26/2019 | Partial Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 1/3/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Pre-Inspection | 1/6/2020 | Partial Inspection | AJA COLLAY |
| Footing/Foundation/Slab | 1/8/2020 | Partial Approval | AJA COLLAY |
| Excavation/Setback/Form/Re-Bar | 1/27/2020 | Approved | AJA COLLAY |
| PLUMBING-Rough | 2/18/2020 | Partial Approval | AJA COLLAY |
| Wood Frame | 2/18/2020 | Partial Approval | AJA COLLAY |
| Insulation | 2/21/2020 | Partial Approval | AJA COLLAY |
| Deputy Steel/Welding | 3/4/2020 | Conditional Approval | AJA COLLAY |
| BUILDING-Rough-Frame | 6/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/5/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Special/Order Compliance | 6/16/2020 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/28/2020 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 9/30/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 9/30/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 10/7/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/7/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 10/7/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/16/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 10/16/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/23/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Rough | 10/23/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 11/20/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/20/2020 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 11/20/2020 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 11/20/2020 | Partial Approval | OSVALDO PARAMO |
| Drywall Nailing | 1/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/25/2021 | Corrections Issued | RUBEN SALAS |
| Interior/Exterior Lathing | 1/25/2021 | Not Ready for Inspection | RUBEN SALAS |
| Sewer | 2/10/2021 | Partial Approval | COREY HUPP |
| Sewer | 2/18/2021 | Approved | COREY HUPP |
| Drywall Nailing | 3/11/2021 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 3/11/2021 | Approved | RUBEN SALAS |
| Wood Frame | 3/11/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 9/2/2021 | SGSOV Not Ready | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 9/14/2021 | Approved | RUBEN SALAS |
| Final | 9/14/2021 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 9/14/2021 | Approved | RUBEN SALAS |
| Green Building Final | 9/14/2021 | Corrections Issued | RUBEN SALAS |
| Green Building Rough | 9/14/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 9/14/2021 | SGSOV Not Ready | RUBEN SALAS |
| Smoke Detectors | 9/14/2021 | Approved | RUBEN SALAS |
| Final | 11/30/2021 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 11/30/2021 | Partial Approval | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/30/2021 | SGSOV Not Ready | THOMAS LOGRASSO |
| Final | 12/6/2021 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 12/6/2021 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 12/7/2021 | OK to Issue CofO | THOMAS LOGRASSO |