7154 W FENWICK ST 91042
Certificate Information: 7154 W FENWICK ST 91042
- Application / Permit
- 19014-10000-00113
- Plan Check / Job No.
- B19LA00521
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY ADDITION TO REAR OF EXISTING 1-STORY SFD
- Permit Issued
- Issued on 1/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 1/28/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 1/29/2019 | MOHAMMAD FIROUZBAKHT |
| Building Plans Picked Up | 1/31/2019 | APPLICANT |
| Green Plans Picked Up | 1/31/2019 | APPLICANT |
| Applicant returned to address corrections | 2/21/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 8/1/2019 | EMMANUEL MARTINEZ |
| Issued | 1/10/2020 | LADBS |
| CofO in Progress | 11/10/2021 | MATTHEW NELSON |
| Permit Finaled | 8/5/2022 | DANIEL ORRANTE |
| CofO Issued | 8/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction within easement | Cleared | 2/1/2019 | NADER ISKANDER |
| ZA Case | Cleared | 2/6/2019 | KIT AWAKUNI |
| Green Code | Cleared | 2/22/2019 | SARAH ABOULHOSN |
| Low Impact Development | Cleared | 5/10/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/12/2019 | JAMES MORALEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/22/2019 | ERIK BEASLEY |
| GPI Written Notices | Cleared | 7/31/2019 | EMMANUEL MARTINEZ |
| Grading Pre-Inspection | Cleared | 7/31/2019 | EMMANUEL MARTINEZ |
Contact Information
| Contractor | Ildo Plumbing; Lic. No.: 1009029-C36 | 7154 FIENWICK ST TUJUNGA, CA 91042 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/25/2020 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/26/2020 | Approved | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/31/2020 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 8/31/2020 | Approved | PIERRE VEGA |
| Deputy Drilled-In Anchors | 11/4/2020 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 11/5/2020 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 11/5/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 12/16/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 12/16/2020 | Approved | MATTHEW NELSON |
| Insulation | 12/18/2020 | Approved | MATTHEW NELSON |
| Wood Frame | 12/18/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/23/2020 | Approved | BEAU COLLINS |
| Interior/Exterior Lathing | 12/23/2020 | Partial Approval | BEAU COLLINS |
| Interior/Exterior Lathing | 2/19/2021 | Approved | MATTHEW NELSON |
| Shower Pan | 2/19/2021 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 4/21/2021 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/21/2021 | Approved | MATTHEW NELSON |
| HVAC-Rough | 4/21/2021 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 4/21/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/12/2021 | Approved | MATTHEW NELSON |
| Final | 5/12/2021 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 5/12/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 5/12/2021 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 5/12/2021 | Approved | MATTHEW NELSON |
| Final | 10/1/2021 | Conditional Approval | JENNIFER RABUCHIN |
| Final | 11/9/2021 | OK to Issue CofO | MATTHEW NELSON |