4643 E EDELLE PL 90032
Certificate Information: 4643 E EDELLE PL 90032
- Application / Permit
- 19014-10000-00095
- Plan Check / Job No.
- B19LA00402
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground Addition to existing 1-story single family dwelling.
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- Issued on 1/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | MUKUL GUPTA |
| Green Plans Picked Up | 2/6/2019 | APPLICANT |
| Corrections Issued | 2/7/2019 | MUKUL GUPTA |
| Quality Review Completed | 2/14/2019 | MOHAMMAD FIROUZBAKHT |
| Applicant returned to address corrections | 9/1/2020 | SAMUEL GONZALEZ |
| Plan Check Approved | 1/4/2021 | SAMUEL GONZALEZ |
| Issued | 1/13/2021 | APPLICANT |
| Building Plans Picked Up | 1/19/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2020 | THOMAS LANG |
| Grading Pre-Inspection | Cleared | 1/24/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 1/24/2020 | DONALD CRICHLOW |
| Roof/Waste drainage to street | Cleared | 1/24/2020 | THOMAS LANG |
| Sewer availability | Cleared | 1/24/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 2/11/2020 | AMMAR ELTAWIL |
| "D" conditions | Cleared | 7/1/2020 | JOE LUCKEY |
| "Q" conditions | Cleared | 7/1/2020 | JOE LUCKEY |
| ZI | Cleared | 7/1/2020 | JOE LUCKEY |
| Hydrant and Access approval | Cleared | 7/17/2020 | KURT CORRAL |
| GPI Written Notices | Cleared | 12/7/2020 | MUKUL GUPTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 7333 RANCHITO AVE VAN NUYS, CA 91405 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/26/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 3/11/2021 | Partial Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 3/18/2021 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2021 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 5/12/2021 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 5/17/2021 | Approved | COREY HUPP |
| Green Building Rough | 5/17/2021 | Approved | COREY HUPP |
| Insulation | 5/24/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 5/26/2021 | Partial Approval | COREY HUPP |
| Shower Pan | 5/26/2021 | Approved | COREY HUPP |
| Drywall Nailing | 6/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/1/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/7/2021 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 12/7/2021 | Approved | COREY HUPP |
| Green Building Final | 12/7/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 12/7/2021 | Approved | COREY HUPP |
| Final | 4/1/2022 | Not Ready for Inspection | AMY COLIN |
| Green Building Final | 4/1/2022 | Not Ready for Inspection | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2022 | SGSOV Not Ready | AMY COLIN |
| Special/Order Compliance | 4/1/2022 | Not Ready for Inspection | AMY COLIN |
| Final | 4/4/2022 | Partial Inspection | AMY COLIN |
| Green Building Final | 4/4/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | AMY COLIN |
| Final | 9/14/2022 | Corrections Issued | AMY COLIN |