4643 E EDELLE PL 90032

Certificate Information: 4643 E EDELLE PL 90032

Application / Permit
19014-10000-00095
Plan Check / Job No.
B19LA00402
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground Addition to existing 1-story single family dwelling.
Permit Issued
Issued on 1/13/2021
Issuing Office
Current Status
Issued on 1/13/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/8/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 MUKUL GUPTA
Green Plans Picked Up 2/6/2019 APPLICANT
Corrections Issued 2/7/2019 MUKUL GUPTA
Quality Review Completed 2/14/2019 MOHAMMAD FIROUZBAKHT
Applicant returned to address corrections 9/1/2020 SAMUEL GONZALEZ
Plan Check Approved 1/4/2021 SAMUEL GONZALEZ
Issued 1/13/2021 APPLICANT
Building Plans Picked Up 1/19/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/24/2020 THOMAS LANG
Grading Pre-Inspection Cleared 1/24/2020 PATRICK MISCHLICH
Green Code Cleared 1/24/2020 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 1/24/2020 THOMAS LANG
Sewer availability Cleared 1/24/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 1/29/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 1/29/2020 THOMAS LANG
BHO/Hillside ordinance Cleared 1/29/2020 THOMAS LANG
Low Impact Development Cleared 2/11/2020 AMMAR ELTAWIL
"D" conditions Cleared 7/1/2020 JOE LUCKEY
"Q" conditions Cleared 7/1/2020 JOE LUCKEY
ZI Cleared 7/1/2020 JOE LUCKEY
Hydrant and Access approval Cleared 7/17/2020 KURT CORRAL
GPI Written Notices Cleared 12/7/2020 MUKUL GUPTA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/26/2021 Approved COREY HUPP
PLUMBING-Rough 3/11/2021 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 3/18/2021 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 4/20/2021 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 5/12/2021 Approved COREY HUPP
BUILDING-Rough-Frame 5/17/2021 Approved COREY HUPP
Green Building Rough 5/17/2021 Approved COREY HUPP
Insulation 5/24/2021 Approved COREY HUPP
Interior/Exterior Lathing 5/26/2021 Partial Approval COREY HUPP
Shower Pan 5/26/2021 Approved COREY HUPP
Drywall Nailing 6/1/2021 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/1/2021 Approved CHRISTOPHER DELLEFIELD
Final 12/7/2021 Corrections Issued COREY HUPP
Footing/Foundation/Slab 12/7/2021 Approved COREY HUPP
Green Building Final 12/7/2021 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Not Ready COREY HUPP
Smoke Detectors 12/7/2021 Approved COREY HUPP
Final 4/1/2022 Not Ready for Inspection AMY COLIN
Green Building Final 4/1/2022 Not Ready for Inspection AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Not Ready AMY COLIN
Special/Order Compliance 4/1/2022 Not Ready for Inspection AMY COLIN
Final 4/4/2022 Partial Inspection AMY COLIN
Green Building Final 4/4/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/4/2022 SGSOV Approved AMY COLIN
Final 9/14/2022 Corrections Issued AMY COLIN