2822 N ROSANNA ST 90039

Certificate Information: 2822 N ROSANNA ST 90039

Application / Permit
19014-10000-00091
Plan Check / Job No.
B19LA00374
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
368 SF ADDITION TO (E) SFD TO INCLUDE: (1) NEW RESTROOM AND NEW BEDROOM, (1) REMODELED RESTROOM AND REMODELED KITCHEN. UPGRADE MSP TO 200A AND (N) TANKLESS WH.
Permit Issued
Issued on 2/19/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/8/2019 APPLICANT
Assigned to Plan Check Engineer 1/8/2019 GEORGE ALVAREZ
Corrections Issued 1/8/2019 GEORGE ALVAREZ
Applicant returned to address corrections 1/18/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 2/19/2020 KEVIN MORALES
Issued 2/19/2020 LADBS
CofO in Progress 4/12/2022 KATHRYN BUTTERWORTH
Permit Finaled 4/13/2022 DEROLD HAUFF
CofO Issued 4/13/2022 DEROLD HAUFF
Permit Finaled 4/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/18/2019 NAZILA NOORIFAR
Roof/Waste drainage to street Cleared 1/18/2019 NAZILA NOORIFAR
Sewer availability Cleared 1/18/2019 NAZILA NOORIFAR

Contact Information

Contractor Owner-Builder       ,
Engineer Finley,, Lawrence Rufus; Lic. No.: C46606 1178 E 9TH ST      LONG BEACH, CA 90813

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/24/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Approved GORDON ZUBER
Floor/Roof Diaphrgm/Shear Wall 4/14/2020 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 10/8/2020 Not Ready for Inspection DONALD CRICHLOW
HVAC-Rough 10/8/2020 Not Ready for Inspection DONALD CRICHLOW
PLUMBING-Rough 10/8/2020 Not Ready for Inspection DONALD CRICHLOW
BUILDING-Rough-Frame 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 11/6/2020 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 11/17/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/17/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 11/17/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 11/17/2020 Approved KATHRYN BUTTERWORTH
MERV13>=Rough 11/17/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 11/17/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/25/2020 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/25/2020 Approved KATHRYN BUTTERWORTH
Green Building Rough 11/25/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 11/25/2020 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 11/25/2020 Approved KATHRYN BUTTERWORTH
Insulation 12/2/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 12/9/2020 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 12/9/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/9/2022 Corrections Issued KATHRYN BUTTERWORTH
Final 2/17/2022 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 2/17/2022 Approved KATHRYN BUTTERWORTH
MERV13>=Final 2/17/2022 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
Smoke Detectors 2/17/2022 Approved KATHRYN BUTTERWORTH
Final 2/23/2022 Corrections Issued KATHRYN BUTTERWORTH
Final 3/1/2022 Corrections Issued KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Approved KATHRYN BUTTERWORTH
Final 4/7/2022 OK to Issue CofO KATHRYN BUTTERWORTH