6549 N FIGUEROA ST 90042
Certificate Information: 6549 N FIGUEROA ST 90042
- Application / Permit
- 19014-10000-00079
- Plan Check / Job No.
- B19LA00325
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) 1-CAR GARAGE TO BE CONVERTED INTO ADU PER AB494 AND SB 229. ADDITION FOR NEW BATHROOM.
- Permit Issued
- Issued on 2/6/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2019 | SAM CHANG |
| Green Plans Picked Up | 2/12/2019 | APPLICANT |
| Corrections Issued | 2/15/2019 | SAM CHANG |
| Quality Review Completed | 2/25/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 2/25/2019 | APPLICANT |
| Applicant returned to address corrections | 2/4/2020 | SAM CHANG |
| Plan Check Approved | 2/6/2020 | SAM CHANG |
| Issued | 2/6/2020 | LADBS |
| CofO in Progress | 12/9/2021 | CRAIG VAUGHAN |
| Permit Finaled | 1/10/2022 | DEROLD HAUFF |
| CofO Issued | 1/10/2022 | DEROLD HAUFF |
| Permit Finaled | 1/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2019 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 6/18/2019 | GEORGE SUCHAND |
| Green Code | Cleared | 1/30/2020 | KHEDER ALRAZAA |
| Grading Pre-Inspection | Cleared | 2/3/2020 | PATRICK MISCHLICH |
| Sewer availability | Cleared | 2/4/2020 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/4/2020 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/4/2020 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/12/2020 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/3/2020 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 9/3/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/20/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/20/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Wood Frame | 11/20/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 12/17/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 12/17/2020 | Partial Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 12/22/2020 | Partial Inspection | OSVALDO PARAMO |
| HVAC-Final | 12/22/2020 | Approved | OSVALDO PARAMO |
| Insulation | 12/24/2020 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 1/20/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 1/21/2021 | Not Ready for Inspection | COREY HUPP |
| Interior/Exterior Lathing | 2/8/2021 | Partial Approval | CRAIG VAUGHAN |
| Underground Mechanical | 3/1/2021 | Partial Approval | CRAIG VAUGHAN |
| Gas Test | 6/21/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 6/21/2021 | Approved | CRAIG VAUGHAN |
| Sewer | 6/21/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Shower Pan | 6/21/2021 | Approved | CRAIG VAUGHAN |
| Sewer | 6/23/2021 | Not Ready for Inspection | COREY HUPP |
| Sewer | 6/29/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/23/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/30/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/30/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 9/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 9/30/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/30/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 9/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 9/30/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Smoke Detectors | 9/30/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 11/15/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/3/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Final | 12/3/2021 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Grading Pre-Inspection | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 12/3/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 12/3/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 12/3/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 12/3/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 12/8/2021 | Approved | CRAIG VAUGHAN |
| Final | 12/8/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| PLUMBING-Final | 12/8/2021 | Approved | CRAIG VAUGHAN |