7824 N KENTLAND AVE 91304

Certificate Information: 7824 N KENTLAND AVE 91304

Application / Permit
19014-10000-00025
Plan Check / Job No.
B19LA00105
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story single family dwelling involved in fire rebuild structure. Propose 35'-10"x 50'-3" odd shaped ground floor addition
Permit Issued
Issued on 4/18/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2019 APPLICANT
Assigned to Plan Check Engineer 1/10/2019 VU NGUYEN
Corrections Issued 1/11/2019 VU NGUYEN
Quality Review Completed 1/11/2019 MICHAEL PEREZ
Building Plans Picked Up 1/11/2019 APPLICANT
Green Plans Picked Up 3/12/2019 APPLICANT
Plan Check Approved 4/18/2019 VU NGUYEN
Issued 4/18/2019 LADBS
CofO in Progress 8/13/2020 DAVID STEPANYAN
Permit Finaled 8/17/2020 DONALD SUNSERI
CofO Issued 8/17/2020 DONALD SUNSERI
Permit Finaled 8/17/2020 DONALD SUNSERI

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/21/2019 ERIK BEASLEY
Hydrant and Access approval Cleared 2/21/2019 GEORGE SUCHAND
Sewer availability Cleared 2/21/2019 ERIK BEASLEY
Low Impact Development Cleared 3/12/2019 MITESH PATEL
Green Code Cleared 4/2/2019 SARAH ABOULHOSN
Roof/Waste drainage to street Cleared 4/2/2019 ERIK BEASLEY

Contact Information

Contractor Baldwin Builders; Lic. No.: 992380-B 482 WEST ARROW HIGHWAY SUITE M      SAN DIMAS, CA 91773
Engineer Runyan,, William Robert; Lic. No.: C32138 10213 HEATHER ST      ALTA LOMA, CA 91737

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/21/2019 Corrections Issued PETER FOLLING
PLUMBING-Rough 5/23/2019 Corrections Issued PETER FOLLING
PLUMBING-Rough 5/28/2019 No Access for Inspection PETER FOLLING
PLUMBING-Rough 5/31/2019 Partial Approval PETER FOLLING
Deputy Drilled-In Anchors 6/4/2019 No Access for Inspection PETER FOLLING
Footing/Foundation/Slab 6/6/2019 Approved PETER FOLLING
BUILDING-Rough-Frame 9/19/2019 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 9/19/2019 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 9/19/2019 Approved PETER FOLLING
Green Building Rough 9/19/2019 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 10/22/2019 Approved PETER FOLLING
BUILDING-Rough-Frame 11/4/2019 Not Ready for Inspection PETER FOLLING
Green Building Rough 11/4/2019 Not Ready for Inspection PETER FOLLING
Interior/Exterior Lathing 11/4/2019 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 11/14/2019 Not Ready for Inspection PETER FOLLING
Green Building Rough 11/14/2019 Approved PETER FOLLING
PLUMBING-Rough 11/14/2019 Approved PETER FOLLING
BUILDING-Rough-Frame 12/3/2019 Approved PETER FOLLING
HVAC-Rough 12/3/2019 Approved PETER FOLLING
Insulation 12/10/2019 Approved PETER FOLLING
Drywall Nailing 1/21/2020 Approved PETER FOLLING
ELECTRICAL-Final 4/8/2020 Approved DAVID STEPANYAN
Underground Mechanical 4/8/2020 Partial Approval DAVID STEPANYAN
Final 5/18/2020 Corrections Issued DAVID STEPANYAN
Green Building Final 5/18/2020 Approved DAVID STEPANYAN
HVAC-Final 5/18/2020 Approved DAVID STEPANYAN
PLUMBING-Final 5/18/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/18/2020 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 5/18/2020 Approved DAVID STEPANYAN
Final 5/28/2020 Corrections Issued DAVID STEPANYAN
Gas Test 5/28/2020 Not Ready for Inspection DAVID STEPANYAN
Interior/Exterior Lathing 5/28/2020 Not Ready for Inspection DAVID STEPANYAN
PLUMBING-Final 5/28/2020 Not Ready for Inspection DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/28/2020 SGSOV Not Ready DAVID STEPANYAN
Interior/Exterior Lathing 6/9/2020 Approved DAVID STEPANYAN
PLUMBING-Final 6/9/2020 Approved DAVID STEPANYAN
Service/Power Release 6/9/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved DAVID STEPANYAN
Sewer 7/28/2020 Corrections Issued DAVID STEPANYAN
Final 8/3/2020 Corrections Issued DAVID STEPANYAN
Sewer 8/3/2020 Approved DAVID STEPANYAN
Final 8/7/2020 Not Ready for Inspection DAVID STEPANYAN
Final 8/13/2020 OK to Issue CofO DAVID STEPANYAN