1135 N AVENUE 64 90042

Certificate Information: 1135 N AVENUE 64 90042

Application / Permit
19012-10000-00007
Plan Check / Job No.
B19LA15723
Group
Building
Type
Bldg-Relocation
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
RELOCATE HOME FROM 1025 S. MARIPOSA AVE TO 1135 N. AVENUE 64. COMBINE RELOCATED DWELLING WITH EXISTING DWELLING ON HOST SITE TO FORM A LARGER HOME. RELOCATED HOME TO BE IN FRONT FACING AVE 64 AND EXISTING HOME MOVE 40 FEET BACKWARD TO CONNECT AT BACK SIDE.PER DIR-2019-2102-COA
Permit Issued
Issued on 12/24/2019
Issuing Office
Metro
Current Status
CofO Issued on 6/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2019 APPLICANT
Assigned to Plan Check Engineer 8/15/2019 ARSALAN SHABESTARI
Corrections Issued 8/20/2019 ARSALAN SHABESTARI
Green Plans Picked Up 8/22/2019 APPLICANT
Quality Review Completed 9/1/2019 YOUNG KIM
Building Plans Picked Up 9/12/2019 APPLICANT
Plan Check Approved 12/20/2019 ARSALAN SHABESTARI
Issued 12/24/2019 LADBS
CofO in Progress 5/29/2025 DAVID WILLIAMS
No Progress 6/3/2025 DEROLD HAUFF
CofO in Progress 6/3/2025 DEROLD HAUFF
Permit Finaled 6/12/2025 DEROLD HAUFF
CofO Issued 6/12/2025 DEROLD HAUFF
Permit Finaled 6/12/2025 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 8/20/2019 KATIE DEBIASE
ZI Cleared 8/20/2019 KATIE DEBIASE
Project located in CRA area Cleared 9/5/2019 JIM URQUHART
ZA Case Cleared 9/5/2019 JOE LUCKEY
ZA Case Cleared 9/5/2019 JOE LUCKEY
ZA Case Cleared 9/5/2019 JOE LUCKEY
BHO/Hillside ordinance Cleared 9/17/2019 JAMES MORALEZ
BHO/Hillside ordinance Cleared 9/17/2019 JAMES MORALEZ
BHO/Hillside ordinance Cleared 9/17/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 10/1/2019 JEANETTE VONG
Hydrant and Access approval Cleared 10/1/2019 JEREMY CARTER
Sewer availability Cleared 10/1/2019 JEANETTE VONG
Miscellaneous Cleared 10/15/2019 KATIE DEBIASE
Grading Pre-Inspection Cleared 11/8/2019 ARSALAN SHABESTARI
Green Code Cleared 11/8/2019 ARSALAN SHABESTARI
Low Impact Development Cleared 11/21/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 11/21/2019 THAN WIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2021 Conditional Approval RUBEN SALAS
BUILDING-Rough-Frame 2/8/2021 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 3/26/2021 Approved RUBEN SALAS
Special/Order Compliance 4/12/2021 Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 4/20/2021 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval RUBEN SALAS
Shower Pan 6/13/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Shower Pan 6/14/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 11/4/2024 Approved ALIZAH MAYAGOITIA
Pre-Inspection 3/26/2025 Partial Inspection RUBEN SALAS
Final 5/5/2025 Corrections Issued DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Approved DAVID WILLIAMS
Final 5/29/2025 OK to Issue CofO DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 5/29/2025 Approved DAVID WILLIAMS