1648-1650 W 35TH ST 90018

Certificate Information: 1648-1650 W 35TH ST 90018

Application / Permit
19010-70000-06541
Plan Check / Job No.
B19SL01918
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW THREE STORY DUPLEX WITH ATTACHED GARAGE
Permit Issued
Issued on 7/20/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 DINA ELKINAWY
Corrections Issued 2/23/2020 DINA ELKINAWY
Green Plans Picked Up 4/23/2020 APPLICANT
Quality Review Completed 9/28/2020 QUAN NGHIEM
Applicant returned to address corrections 5/12/2021 DINA ELKINAWY
Plan Check Approved 5/12/2021 DINA ELKINAWY
Issued 7/20/2022 APPLICANT
CofO in Progress 10/17/2024 SABAS ALONSO
Permit Finaled 11/1/2024 DEROLD HAUFF
CofO Issued 11/1/2024 DEROLD HAUFF
Permit Finaled 11/1/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/1/2020 WALLIE JONG
Permit Cleared 12/1/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/8/2020 WALLIE JONG
Sewer availability Cleared 12/15/2020 WALLIE JONG
ZI Cleared 1/7/2021 RICHARD REASER
Hydrant and Access approval Cleared 1/15/2021 KURT CORRAL
Low Impact Development Cleared 3/25/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 4/26/2021 JEANIE LAM
Green Code Cleared 5/12/2021 COLIN LOREDO

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/3/2022 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 12/1/2022 Partial Approval SABAS ALONSO
METHANE-Barrier 12/1/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 12/1/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Subgrade 12/9/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 12/15/2022 Approved SABAS ALONSO
METHANE-Barrier 12/15/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/25/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/30/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 8/11/2023 Approved SABAS ALONSO
PLUMBING-Rough 8/11/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 11/1/2023 Approved SABAS ALONSO
Green Building Rough 11/1/2023 Approved SABAS ALONSO
HVAC-Rough 11/1/2023 Approved SABAS ALONSO
METHANE-Rough 11/1/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/1/2023 Approved SABAS ALONSO
Insulation 11/15/2023 Approved SABAS ALONSO
Drywall Nailing 11/22/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 11/22/2023 Partial Approval SABAS ALONSO
Final 9/24/2024 Corrections Issued SABAS ALONSO
Green Building Final 9/24/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/24/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 9/24/2024 Approved SABAS ALONSO
Smoke Detectors 9/24/2024 Approved SABAS ALONSO
Final 10/15/2024 OK to Issue CofO SABAS ALONSO