859 W 88TH ST 90044
Certificate Information: 859 W 88TH ST 90044
- Application / Permit
- 19010-70000-06521
- Plan Check / Job No.
- B19SL01910
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story Accessory Dwelling Unit per WFPP.
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Current Status
- CofO Issued on 10/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | ERIC WONG |
| Corrections Issued | 2/19/2020 | ERIC WONG |
| Quality Review Completed | 2/19/2020 | KEN GILL |
| Building Plans Picked Up | 2/25/2020 | APPLICANT |
| Plan Check Approved | 10/1/2020 | ERIC WONG |
| Issued | 10/23/2020 | APPLICANT |
| CofO in Progress | 10/1/2021 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 10/2/2021 | DEROLD HAUFF |
| CofO Issued | 10/2/2021 | DEROLD HAUFF |
| Permit Finaled | 10/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/28/2020 | JEANETTE VONG |
| Green Code | Cleared | 3/5/2020 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 7/21/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 9/1/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/22/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/19/2020 | Corrections Issued | JOHN KLARIN |
| Underground Mechanical | 11/19/2020 | Not Ready for Inspection | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 11/30/2020 | No Access for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/8/2020 | Not Ready for Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/15/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 12/21/2020 | No Access for Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/5/2021 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 1/5/2021 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2021 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 2/10/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/24/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/24/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/24/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/24/2021 | Conditional Approval | FREDDIE RIVERA |
| Wood Frame | 2/24/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/5/2021 | Conditional Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/5/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Insulation | 3/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/5/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 3/5/2021 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/11/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/11/2021 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 3/11/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/10/2021 | Conditional Approval | DAVID FEILER |
| Final | 5/10/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 5/10/2021 | Approved | DAVID FEILER |
| Green Building Final | 5/10/2021 | Not Ready for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 5/10/2021 | SGSOV Not Ready | DAVID FEILER |
| Service/Power Release | 5/10/2021 | Not Ready for Inspection | DAVID FEILER |
| Smoke Detectors | 5/10/2021 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 5/10/2021 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Final | 6/7/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 6/7/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 6/7/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 6/7/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Final | 6/7/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 6/7/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Service/Power Release | 6/7/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 6/7/2021 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/2/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/2/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 7/2/2021 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/16/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Final | 8/16/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/16/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/16/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/16/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/16/2021 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 8/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/17/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 8/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 8/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 8/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 8/17/2021 | Approved | ALEJANDRO DE ARTOLA |
| Final | 8/18/2021 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/30/2021 | OK to Issue CofO | ALEJANDRO DE ARTOLA |