5526 E RANGE VIEW AVE 90042
Certificate Information: 5526 E RANGE VIEW AVE 90042
- Application / Permit
- 19010-70000-06310
- Plan Check / Job No.
- B19SL01890
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED ONE CAR GARAGE
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 1/14/2020 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 1/14/2020 | QUAN NGHIEM |
| Plan Check Approved | 2/14/2020 | TEODORO DIAZ RODRIGUEZ |
| Issued | 3/26/2021 | APPLICANT |
| Building Plans Picked Up | 3/31/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | CRAIG VAUGHAN |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2020 | EMIL KYUPELYAN |
| Hydrant and Access approval | Cleared | 2/10/2020 | JEREMY CARTER |
| Sewer availability | Cleared | 2/10/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 2/13/2020 | TEODORO DIAZ RODRIGUEZ |
| Low Impact Development | Cleared | 2/13/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | JEANETTE VONG |
| GPI Written Notices | Cleared | 2/14/2020 | TEODORO DIAZ RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 2/14/2020 | TEODORO DIAZ RODRIGUEZ |
Contact Information
| Contractor | G A Design Build; Lic. No.: 941130-B | 8449 EVEREST ST DOWNEY, CA 90242 |
| Engineer | Wong,, Jim Chu Man; Lic. No.: C69393 | PO BOX 373 GLENDORA, CA 91740 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/12/2021 | Corrections Issued | CRAIG VAUGHAN |
| Underground Mechanical | 4/12/2021 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/21/2021 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/26/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Not Ready for Inspection | COREY HUPP |
| PLUMBING-Rough | 6/4/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2021 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/16/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 6/21/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Rough | 6/21/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/21/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 6/24/2021 | Approved | COREY HUPP |
| HVAC-Rough | 6/24/2021 | Approved | COREY HUPP |
| Wood Frame | 7/14/2021 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/21/2021 | Conditional Approval | COREY HUPP |
| Green Building Rough | 7/21/2021 | Approved | COREY HUPP |
| Verify Sprinkler Sign Off | 7/21/2021 | Not Ready for Inspection | COREY HUPP |
| Insulation | 7/29/2021 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 7/29/2021 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/18/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 8/18/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/18/2021 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 8/18/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/1/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/1/2021 | Approved | CRAIG VAUGHAN |
| Shower Pan | 9/10/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| Final | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/7/2022 | Approved | SCOTT FINNILA |
| Gas Test | 7/7/2022 | Approved | SCOTT FINNILA |
| Green Building Final | 7/7/2022 | Approved | SCOTT FINNILA |
| HVAC-Final | 7/7/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 7/7/2022 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Not Ready | SCOTT FINNILA |
| Service/Power Release | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| Smoke Detectors | 7/7/2022 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 7/28/2022 | No Access for Inspection | CRAIG VAUGHAN |
| Gas Test | 7/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| HVAC-Final | 7/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 7/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Service/Power Release | 7/28/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Final | 8/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 8/9/2022 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 8/9/2022 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 8/9/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 8/9/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 8/9/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 8/15/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/15/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| Gas Test | 8/15/2022 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 8/15/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 8/15/2022 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 8/15/2022 | Approved | CRAIG VAUGHAN |