11030 N DE HAVEN AVE 91331
Certificate Information: 11030 N DE HAVEN AVE 91331
- Application / Permit
- 19010-70000-06190
- Plan Check / Job No.
- B19SL01880
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT (1100 sq ft) AT REAR per per ordinance LAMC 12.22 A.33 (b)(6)
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 5/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | MONICA RAMIREZ |
| Corrections Issued | 2/18/2020 | MONICA RAMIREZ |
| Quality Review Completed | 2/22/2020 | STANLEY RAAP |
| Building Plans Picked Up | 2/28/2020 | APPLICANT |
| Green Plans Picked Up | 4/21/2020 | APPLICANT |
| Plan Check Approved | 7/16/2020 | MONICA RAMIREZ |
| Issued | 4/22/2021 | APPLICANT |
| CofO in Progress | 5/2/2023 | MICHEL ABAJAN |
| CofO Issued | 5/3/2023 | MICHAEL SMITH |
| Permit Finaled | 5/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 2/28/2020 | JEREMY CARTER |
| Permit | Cleared | 2/28/2020 | JEANIE LAM |
| Sewer availability | Cleared | 2/28/2020 | JEANIE LAM |
| Green Code | Cleared | 3/12/2020 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 5/28/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/3/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Felix Bolivar; Lic. No.: C64738 | 14619 CATALINA AVE GARDENA, CA 90247 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/28/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/28/2021 | Corrections Issued | MICHEL ABAJAN |
| Pre-Inspection | 9/28/2021 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 9/28/2021 | Corrections Issued | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Corrections Issued | JOHN HAYES |
| Pre-Inspection | 9/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 9/29/2021 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 9/30/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 9/30/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/30/2021 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 9/30/2021 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/12/2021 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/12/2021 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Rough | 11/12/2021 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 11/12/2021 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 11/12/2021 | No Access for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 11/12/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/17/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/17/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/17/2021 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 11/17/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/17/2021 | Approved | MICHEL ABAJAN |
| Insulation | 12/6/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/6/2021 | Partial Inspection | WILLIAM KUEHN |
| Pre-Inspection | 12/6/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| Drywall Nailing | 12/14/2021 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 3/30/2022 | Partial Inspection | MICHEL ABAJAN |
| Green Building Final | 3/30/2022 | Partial Inspection | MICHEL ABAJAN |
| HVAC-Final | 3/30/2022 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 3/30/2022 | Partial Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 3/30/2022 | Partial Inspection | MICHEL ABAJAN |
| Smoke Detectors | 3/30/2022 | Partial Inspection | MICHEL ABAJAN |
| Underground Mechanical | 3/30/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/25/2023 | Approved | MICHEL ABAJAN |
| Final | 4/25/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/25/2023 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/25/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/25/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 4/25/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 4/25/2023 | Corrections Issued | MICHEL ABAJAN |
| Final | 5/1/2023 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 5/1/2023 | Approved | MICHEL ABAJAN |
| Smoke Detectors | 5/1/2023 | Approved | MICHEL ABAJAN |