5401 W CARLIN ST 90016
Certificate Information: 5401 W CARLIN ST 90016
- Application / Permit
- 19010-70000-06177
- Plan Check / Job No.
- B19SL01874
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SINGLE FAMILY DWELLING W/ 2-CAR ATTACHED GARAGE AT FRONT OF LOT.
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Current Status
- CofO Issued on 1/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 2/17/2020 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 2/23/2020 | YOUNG KIM |
| Green Plans Picked Up | 6/19/2020 | APPLICANT |
| Applicant returned to address corrections | 8/20/2020 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 8/25/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 8/26/2020 | FARSHAD ALIMOHAMADI |
| Issued | 9/3/2020 | APPLICANT |
| Building Plans Picked Up | 9/9/2020 | APPLICANT |
| CofO in Progress | 12/23/2021 | RUBEN SALAS |
| Permit Finaled | 1/14/2022 | DEROLD HAUFF |
| CofO Issued | 1/14/2022 | DEROLD HAUFF |
| Permit Finaled | 1/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2020 | JEANETTE VONG |
| Permit | Cleared | 2/27/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/27/2020 | JEANETTE VONG |
| Trees in Parkway | Cleared | 3/13/2020 | JOHN KIM |
| Frnt yard landscape/Water mgmt | Cleared | 5/7/2020 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 5/27/2020 | KURT CORRAL |
| Green Code | Cleared | 6/18/2020 | NEGAR NEJAD |
| Low Impact Development | Cleared | 7/6/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/14/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Lida International Building System; Lic. No.: 1064214-B | 1183 ROLLAND CURTIS PLACE LOS ANGELES, CA 90037 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/19/2020 | Corrections Issued | DONALD CRICHLOW |
| Sewer | 11/2/2020 | Corrections Issued | RUBEN SALAS |
| Sewer | 11/5/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 11/10/2020 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 11/20/2020 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2020 | Not Ready for Inspection | DAVID CHAN |
| Wood Frame | 12/22/2020 | Not Ready for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2021 | Conditional Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Partial Approval | RUBEN SALAS |
| BUILDING-Rough-Frame | 4/12/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2021 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 4/12/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 4/12/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 4/12/2021 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/14/2021 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/14/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 4/14/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/14/2021 | Approved | STUART CHAPMAN |
| Sewer | 4/14/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/23/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/27/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/27/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/27/2021 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 4/27/2021 | Approved | STUART CHAPMAN |
| Insulation | 5/6/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/24/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/1/2021 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/27/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 9/2/2021 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 9/2/2021 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 9/7/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Underground Mechanical | 9/7/2021 | Not Ready for Inspection | ROBERT VORHIS |
| Sewer | 9/9/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 9/9/2021 | Partial Inspection | DAVID FEILER |
| Underground Mechanical | 9/14/2021 | Corrections Issued | CALEB MEISTER |
| Underground Mechanical | 9/16/2021 | Partial Approval | CALEB MEISTER |
| Gas Test | 9/17/2021 | Not Ready for Inspection | ALFREDO BALANDRA |
| Gas Test | 9/20/2021 | Partial Approval | CALEB MEISTER |
| Underground Mechanical | 9/20/2021 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Final | 9/28/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 9/28/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Final | 10/1/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 10/1/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/1/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 10/1/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 10/1/2021 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 10/1/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 10/1/2021 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 10/1/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 10/1/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 10/5/2021 | Corrections Issued | STUART CHAPMAN |
| Final | 10/5/2021 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 10/5/2021 | Corrections Issued | STUART CHAPMAN |
| Service/Power Release | 10/5/2021 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 11/15/2021 | Approved | JOSE AVILA |
| Final | 11/15/2021 | Corrections Issued | JOSE AVILA |
| Green Building Final | 11/15/2021 | Approved | JOSE AVILA |
| HVAC-Final | 11/15/2021 | Approved | JOSE AVILA |
| Service/Power Release | 11/15/2021 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 11/15/2021 | Approved | JOSE AVILA |
| Final | 12/6/2021 | Partial Inspection | JOSE AVILA |
| Service/Power Release | 12/6/2021 | Approved | JOSE AVILA |
| Final | 12/9/2021 | Partial Inspection | JOSE AVILA |
| Final | 12/22/2021 | OK to Issue CofO | JOSE AVILA |