3918 1/2-3/4 S BRIGHTON AVE 90062

Certificate Information: 3918 1/2-3/4 S BRIGHTON AVE 90062

Application / Permit
19010-70000-06143
Plan Check / Job No.
B19SL01865
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED DUPLEX WITH 4-CAR GARAGE AT REAR OF LOT
Permit Issued
Issued on 12/1/2020
Issuing Office
Current Status
CofO Issued on 11/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/17/2020 SINA KHOSRAVI
Corrections Issued 1/22/2020 SINA KHOSRAVI
Quality Review Completed 1/26/2020 YOUNG KIM
Green Plans Picked Up 6/25/2020 APPLICANT
Applicant returned to address corrections 9/4/2020 SINA KHOSRAVI
Applicant returned to address corrections 10/2/2020 SINA KHOSRAVI
Applicant returned to address corrections 11/10/2020 SINA KHOSRAVI
Plan Check Approved 11/16/2020 SINA KHOSRAVI
Building Plans Picked Up 11/17/2020 APPLICANT
Issued 12/1/2020 APPLICANT
CofO in Progress 10/21/2021 SABAS ALONSO
Permit Finaled 11/10/2021 DEROLD HAUFF
CofO Issued 11/10/2021 DEROLD HAUFF
Permit Finaled 11/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/4/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/22/2020 EMIL KYUPELYAN
Green Code Cleared 6/25/2020 SINA KHOSRAVI
Sewer availability Cleared 7/9/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 7/14/2020 KURT CORRAL
Low Impact Development Cleared 7/29/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/5/2020 ROSA SILVA

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/21/2020 Approved ROBERT MCDOWELL
Underground Mechanical 12/21/2020 Approved ROBERT MCDOWELL
Deputy Reinf. Concrete 12/23/2020 Conditional Approval ROBERT MCDOWELL
Footing/Foundation/Slab 12/23/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/2/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 3/19/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 3/19/2021 Approved ROBERT MCDOWELL
Green Building Rough 3/19/2021 Approved ROBERT MCDOWELL
HVAC-Rough 3/19/2021 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/19/2021 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 3/19/2021 Approved ROBERT MCDOWELL
Insulation 3/25/2021 Approved ROBERT MCDOWELL
Drywall Nailing 4/1/2021 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 4/1/2021 Approved ROBERT MCDOWELL
Gas Test 6/18/2021 Approved DAVID FEILER
Sewer 6/18/2021 Approved DAVID FEILER
Underground Mechanical 6/18/2021 Approved DAVID FEILER
Verify Rec and Parks Fee Memo 6/18/2021 Not Ready for Inspection DAVID FEILER
Gas Test 9/23/2021 Approved SABAS ALONSO
Verify Rec and Parks Fee Memo 9/23/2021 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 9/30/2021 Approved SABAS ALONSO
HVAC-Final 9/30/2021 Approved SABAS ALONSO
Final 10/5/2021 Corrections Issued SABAS ALONSO
Green Building Final 10/5/2021 Approved SABAS ALONSO
PLUMBING-Final 10/5/2021 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 10/5/2021 Approved SABAS ALONSO
Smoke Detectors 10/5/2021 Approved SABAS ALONSO
Final 10/21/2021 OK to Issue CofO SABAS ALONSO