1622-1622 1/2 W 36TH PL 90018

Certificate Information: 1622-1622 1/2 W 36TH PL 90018

Application / Permit
19010-70000-06089
Plan Check / Job No.
B19SL01851
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX
Permit Issued
Issued on 7/25/2020
Issuing Office
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 FERNANDO FLORES
Corrections Issued 1/30/2020 FERNANDO FLORES
Quality Review Completed 2/4/2020 ARMEN JIVALAGIAN
Green Plans Picked Up 4/1/2020 APPLICANT
Applicant returned to address corrections 5/29/2020 FERNANDO FLORES
Plan Check Approved 7/8/2020 FERNANDO FLORES
Issued 7/25/2020 APPLICANT
Building Plans Picked Up 7/29/2020 APPLICANT
CofO in Progress 7/15/2021 HORACE FULTZ
Permit Finaled 8/10/2021 DEROLD HAUFF
CofO Issued 8/10/2021 DEROLD HAUFF
Permit Finaled 8/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 2/12/2020 FERNANDO FLORES
Address approval Cleared 3/31/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 4/2/2020 ELENA LOPEZ
Sewer availability Cleared 4/2/2020 ELENA LOPEZ
Hydrant and Access approval Cleared 4/22/2020 KURT CORRAL
Low Impact Development Cleared 5/19/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 5/27/2020 EMIL KYUPELYAN
Trees in Parkway Cleared 7/7/2020 JOHN KIM

Contact Information

Contractor Meza Aurelio; Lic. No.: 1065516-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Engineer Sanchez,, Pablo Beltran; Lic. No.: C86223 1840 S GAFFEY ST 382      SAN PEDRO, CA 90731
Geologist Feucht,, Alex Thomas; Lic. No.: GEO4433 2443 EAGLE HARBOR DRIVE      HENDERSON, NV 890527136

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/13/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 8/24/2020 Approved ROBERT MCDOWELL
METHANE-Barrier 8/24/2020 Approved ROBERT MCDOWELL
METHANE-Subgrade 8/24/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Approval ROBERT MCDOWELL
PLUMBING-Rough 9/1/2020 Not Ready for Inspection ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 9/8/2020 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 9/29/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 10/5/2020 Partial Approval ROBERT MCDOWELL
ELECTRICAL-Rough 10/5/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Approved ROBERT MCDOWELL
Green Building Rough 10/5/2020 Not Ready for Inspection ROBERT MCDOWELL
HVAC-Rough 10/5/2020 Approved ROBERT MCDOWELL
METHANE-Rough 10/5/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 10/5/2020 Approved ROBERT MCDOWELL
Verify Sprinkler Sign Off 10/5/2020 Approved ROBERT MCDOWELL
Insulation 10/26/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 10/26/2020 Approved ROBERT MCDOWELL
Drywall Nailing 11/5/2020 Approved ROBERT MCDOWELL
Green Building Rough 11/5/2020 Approved ROBERT MCDOWELL
Interior/Exterior Lathing 11/5/2020 Approved ROBERT MCDOWELL
ELECTRICAL-Final 1/27/2021 Not Ready for Inspection ROBERT MCDOWELL
Service/Power Release 1/27/2021 Approved ROBERT MCDOWELL
BUILDING-Rough-Frame 4/21/2021 Approved ROBERT MCDOWELL
ELECTRICAL-Final 4/21/2021 Approved ROBERT MCDOWELL
Final 4/21/2021 Corrections Issued ROBERT MCDOWELL
Green Building Final 4/21/2021 Approved ROBERT MCDOWELL
HVAC-Final 4/21/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 4/21/2021 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 4/21/2021 Approved ROBERT MCDOWELL
Final 6/25/2021 OK to Issue CofO HORACE FULTZ