1745 S BERENDO ST 90006

Certificate Information: 1745 S BERENDO ST 90006

Application / Permit
19010-70000-05820
Plan Check / Job No.
B19SL01795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 3 STORY (32.5' X 23') SINGLE FAMILY DWELLING AND ATTACHED 2-CAR GARAGE. ***FRONT***
Permit Issued
Issued on 2/11/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/30/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 MICHAEL LOPEZ
Green Plans Picked Up 1/6/2020 APPLICANT
Corrections Issued 1/7/2020 MICHAEL LOPEZ
Quality Review Completed 1/11/2020 STANLEY RAAP
Building Plans Picked Up 1/17/2020 APPLICANT
Plan Check Approved 2/7/2020 MICHAEL LOPEZ
Issued 2/11/2020 LADBS
CofO in Progress 9/30/2020 DONALD CRICHLOW
Permit Finaled 9/30/2020 DEROLD HAUFF
CofO Issued 9/30/2020 DEROLD HAUFF
Permit Finaled 9/30/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/29/2020 CELINA MORENO
Highway dedication Cleared 1/29/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/4/2020 CELINA MORENO
Green Code Cleared 2/4/2020 NEGAR NEJAD
Hydrant and Access approval Cleared 2/4/2020 GEORGE SUCHAND
Sewer availability Cleared 2/4/2020 CELINA MORENO
Low Impact Development Cleared 2/6/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/6/2020 JEANETTE VONG
Frnt yard landscape/Water mgmt Cleared 2/7/2020 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2020 Conditional Approval SCOTT FINNILA
Sewer 2/21/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 2/21/2020 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 2/28/2020 Approved ROBERT MCDOWELL
Footing/Foundation/Slab 2/28/2020 Approved ROBERT MCDOWELL
METHANE-Barrier 2/28/2020 Approved ROBERT MCDOWELL
METHANE-Subgrade 2/28/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/1/2020 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval KATHRYN BUTTERWORTH
Deputy Wood Construction 4/16/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 5/13/2020 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 5/13/2020 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 5/26/2020 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 6/8/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/12/2020 Partial Approval ENRIQUE MIRELES
Green Building Rough 6/12/2020 Approved ENRIQUE MIRELES
METHANE-Rough 6/12/2020 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 6/12/2020 Approved ENRIQUE MIRELES
Drywall Nailing 6/18/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/18/2020 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/12/2020 Approved KATHRYN BUTTERWORTH
Final 8/12/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Final 8/12/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/12/2020 SGSOV Approved KATHRYN BUTTERWORTH
Service/Power Release 8/12/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 8/12/2020 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 9/17/2020 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 9/17/2020 Approved CRAIG VAUGHAN
Green Building Final 9/17/2020 Not Ready for Inspection CRAIG VAUGHAN
Service/Power Release 9/17/2020 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 9/17/2020 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 9/22/2020 No Access for Inspection COREY HUPP
Final 9/25/2020 Partial Inspection DONALD CRICHLOW
Green Building Final 9/25/2020 Partial Inspection DONALD CRICHLOW
Service/Power Release 9/25/2020 Not Ready for Inspection DONALD CRICHLOW
Smoke Detectors 9/25/2020 Approved DONALD CRICHLOW
Pre-Inspection 9/29/2020 Approved DONALD CRICHLOW
Service/Power Release 9/29/2020 Approved DONALD CRICHLOW
ELECTRICAL-Final 9/30/2020 Approved DONALD CRICHLOW
Final 9/30/2020 OK to Issue CofO DONALD CRICHLOW
Green Building Final 9/30/2020 Approved DONALD CRICHLOW
HVAC-Final 9/30/2020 Approved DONALD CRICHLOW
PLUMBING-Final 9/30/2020 Approved DONALD CRICHLOW
Service/Power Release 9/30/2020 Approved DONALD CRICHLOW