832-832 1/2 N JUNE ST 90038
Certificate Information: 832-832 1/2 N JUNE ST 90038
- Application / Permit
- 19010-70000-05812
- Plan Check / Job No.
- B19SL01793
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX WITH ATTACHED GARAGE AT REAR. SEE COMMENTS.
- Permit Issued
- Issued on 4/15/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2020 | SERGIO GUTIERREZ |
| Corrections Issued | 2/7/2020 | SERGIO GUTIERREZ |
| Quality Review Completed | 2/26/2020 | KESETE HAREGOT |
| Building Plans Picked Up | 3/2/2020 | APPLICANT |
| Green Plans Picked Up | 8/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/25/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/10/2021 | SERGIO GUTIERREZ |
| Issued | 4/15/2021 | APPLICANT |
| CofO in Progress | 7/22/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
| Permit Finaled | 7/30/2023 | DEROLD HAUFF |
| CofO Issued | 7/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 8/5/2020 | ROBIN YAMADA |
| Green Code | Cleared | 8/12/2020 | SERGIO GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | ROSA SILVA |
| Address approval | Cleared | 9/1/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/2/2020 | ROSA SILVA |
| Highway dedication | Cleared | 9/10/2020 | JAMES KHO |
| Hydrant and Access approval | Cleared | 9/16/2020 | MATTHEW CRAIG |
| Sewer availability | Cleared | 9/16/2020 | JEANIE LAM |
| Frnt yard landscape/Water mgmt | Cleared | 12/29/2020 | ANACANY HURTADO |
| ZA Case | Cleared | 12/29/2020 | ANACANY HURTADO |
| Construction near power lines | Cleared | 2/6/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/6/2021 | RIDWAN HARDY |
Contact Information
| Architect | Tavasci,, Robert J; Lic. No.: C26023 | 3351 ORANGEWOOD AVENUE ROSSMOOR, CA 90720 |
| Contractor | Tavasci R J Design Const; Lic. No.: 385183-B | 3351 ORANGEWOOD AVE LOS ALAMITOS, CA 90720 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2021 | Corrections Issued | BRIAN SULLIVAN |
| METHANE-Barrier | 5/24/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Subgrade | 5/24/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 5/24/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/21/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| METHANE-Barrier | 6/21/2021 | Approved | BRIAN SULLIVAN |
| METHANE-Subgrade | 6/21/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 9/24/2021 | Approved | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 9/28/2021 | Conditional Approval | ROBERT CORNELL |
| Footing/Foundation/Slab | 12/2/2021 | Approved | BRIAN SULLIVAN |
| Deputy Wood Construction | 1/13/2022 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 5/26/2022 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Partial Inspection | SCOTT FINNILA |
| PLUMBING-Rough | 7/28/2022 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 10/27/2022 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 10/27/2022 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/27/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 11/21/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Rough | 11/21/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 11/21/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 12/2/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 12/27/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 12/27/2022 | Partial Approval | RUBEN SALAS |
| Shower Pan | 12/27/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 1/24/2023 | Approved | JOAQUIN GREENOUGH |
| Sewer | 3/9/2023 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 3/15/2023 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/21/2023 | Corrections Issued | BRIAN SULLIVAN |
| Gas Test | 4/21/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 4/21/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Final | 4/27/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Gas Test | 4/27/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/5/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 5/24/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 5/24/2023 | Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 5/24/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 5/25/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 5/25/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 5/25/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 5/25/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 5/25/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 5/25/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/16/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 6/16/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 6/16/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 7/20/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |