Deputy Reinf. Concrete
|
4/7/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Reinf. Concrete
|
4/18/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
4/19/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Steel/Welding
|
4/29/2022
|
Conditional Approval
|
NICK DANERI
|
|
Deputy Reinf. Concrete
|
5/16/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
5/17/2022
|
Partial Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
5/18/2022
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
11/1/2023
|
Partial Inspection
|
NICK DANERI
|
|
Green Building Rough
|
11/8/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Piling/Pier/Caisson
|
11/8/2023
|
Partial Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/8/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Deputy Steel/Welding
|
11/14/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
11/16/2023
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/17/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Green Building Rough
|
11/17/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
11/17/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
11/30/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
11/30/2023
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
11/30/2023
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/11/2023
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
12/11/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Verify Sprinkler Sign Off
|
12/11/2023
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
1/5/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
1/5/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
1/5/2024
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Deputy Drilled-In Anchors
|
1/29/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Deputy Drilled-In Anchors
|
2/14/2024
|
Conditional Approval
|
MICHAEL ROSENBERG
|
|
Green Building Rough
|
2/22/2024
|
Not Ready for Inspection
|
JACOB MYERS
|
|
Insulation
|
2/22/2024
|
Approved
|
JACOB MYERS
|
|
Verify Sprinkler Sign Off
|
2/22/2024
|
Not Ready for Inspection
|
JACOB MYERS
|
|
Footing/Foundation/Slab
|
2/27/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Rough
|
2/27/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
2/27/2024
|
Partial Inspection
|
NICK DANERI
|
|
Wood Frame
|
2/27/2024
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/1/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/17/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
4/17/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
4/17/2024
|
Partial Inspection
|
NICK DANERI
|
|
Drywall Nailing
|
4/25/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
4/25/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
4/25/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
5/8/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
5/8/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
5/8/2024
|
Partial Approval
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
5/8/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
5/17/2024
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
7/23/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
7/23/2024
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
7/23/2024
|
Approved
|
NICK DANERI
|
|
Drywall Nailing
|
7/29/2024
|
Partial Approval
|
NICK DANERI
|
|
Green Building Rough
|
7/29/2024
|
Approved
|
NICK DANERI
|
|
Interior/Exterior Lathing
|
9/6/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Masonry Wall/Backfill
|
9/6/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
|
Excavation/Setback/Form/Re-Bar
|
9/20/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Excavation/Setback/Form/Re-Bar
|
10/1/2024
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
10/23/2024
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2025
|
Partial Approval
|
NICK DANERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/26/2025
|
Partial Approval
|
NICK DANERI
|
|
Drywall Nailing
|
3/12/2025
|
Approved
|
NICK DANERI
|
|
Final
|
3/12/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
3/12/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Green Building Final
|
3/12/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
3/12/2025
|
SGSOV Not Ready
|
NICK DANERI
|
|
Smoke Detectors
|
3/12/2025
|
Partial Approval
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
3/12/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
3/12/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Final
|
5/8/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
Footing/Foundation/Slab
|
5/8/2025
|
Approved
|
NICK DANERI
|
|
Green Building Final
|
5/8/2025
|
Not Ready for Inspection
|
NICK DANERI
|
|
SGSOV-Seismic Gas S/O Valve
|
5/8/2025
|
SGSOV Approved
|
NICK DANERI
|
|
Smoke Detectors
|
5/8/2025
|
Approved
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
5/8/2025
|
Approved
|
NICK DANERI
|
|
Wood Frame
|
5/8/2025
|
Approved
|
NICK DANERI
|
|
Special/Order Compliance
|
5/27/2025
|
Partial Inspection
|
NICK DANERI
|
|
Final
|
6/6/2025
|
Conditional Approval
|
JOEY BUCHANAN
|
|
Green Building Final
|
6/6/2025
|
Approved
|
JOEY BUCHANAN
|
|
Special/Order Compliance
|
6/10/2025
|
Approved
|
JOEY BUCHANAN
|