1106 S KENMORE AVE 1-7 90006

Certificate Information: 1106 S KENMORE AVE 1-7 90006

Application / Permit
19010-70000-05592
Plan Check / Job No.
B19SL01746
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 3 - Story 7 units Apartment building.
Permit Issued
Issued on 11/29/2021
Issuing Office
Current Status
CofO Issued on 6/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2019 APPLICANT
Assigned to Plan Check Engineer 1/16/2020 SALVADOR QUINTANILLA
Disabled Access Plans Picked Up 1/31/2020 APPLICANT
Corrections Issued 2/10/2020 SALVADOR QUINTANILLA
Quality Review Completed 2/12/2020 KEN GILL
Applicant returned to address corrections 3/19/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/24/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 3/25/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/2/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 6/3/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 11/24/2020 SALVADOR QUINTANILLA
Applicant returned to address corrections 11/25/2020 SALVADOR QUINTANILLA
Green Plans Picked Up 12/16/2020 APPLICANT
Applicant returned to address corrections 5/26/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 5/27/2021 SALVADOR QUINTANILLA
Applicant returned to address corrections 7/22/2021 SALVADOR QUINTANILLA
Plan Check Approved 8/2/2021 SALVADOR QUINTANILLA
Issued 11/29/2021 APPLICANT
Building Plans Picked Up 12/14/2021 APPLICANT
Permit Finaled 6/10/2025 ERNESTO CORRAL
CofO Issued 6/10/2025 ERNESTO CORRAL
Permit Finaled 6/10/2025 ERNESTO CORRAL

Permit Application Clearance Information

Fire Marshall Fire Life Safety Cleared 6/30/2020 ANDREW KO
Address approval Cleared 7/29/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 7/29/2020 JEANIE LAM
Highway dedication Cleared 7/29/2020 JEANIE LAM
Frnt yard landscape/Water mgmt Cleared 9/21/2020 MIGUEL GAMBOA
Opn space landscape/Water mgmt Cleared 9/21/2020 MIGUEL GAMBOA
Miscellaneous Cleared 9/22/2020 KEVIN ARUCAN
Green Code Cleared 11/5/2020 DONALD CRICHLOW
DAS Clearance Cleared 11/18/2020 SHINE LIN
Hydrant and Access approval Cleared 12/11/2020 MATTHEW CRAIG
Building over 3-story or 36-ft Cleared 3/30/2021 CALOSHA APPROVED
Sewer availability Cleared 4/13/2021 JEANIE LAM
Low Impact Development Cleared 6/28/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/28/2021 JEANIE LAM

Contact Information

Architect Kang,, Hyeung Seok; Lic. No.: C38323 3530 WILSHIRE BLVD #1830      LOS ANGELES, CA 90010
Contractor New Creation Engineering & Builders Inc; Lic. No.: 768842-B 17809 CLARK AVENUE      BELLFLOWER, CA 90706
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/7/2022 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 4/18/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/19/2022 Conditional Approval NICK DANERI
Deputy Steel/Welding 4/29/2022 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/16/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/17/2022 Partial Approval TED RIES
Deputy Reinf. Concrete 5/18/2022 Conditional Approval RAFAEL ESPINOZA
Special/Order Compliance 11/1/2023 Partial Inspection NICK DANERI
Green Building Rough 11/8/2023 Not Ready for Inspection NICK DANERI
Piling/Pier/Caisson 11/8/2023 Partial Inspection NICK DANERI
Verify Sprinkler Sign Off 11/8/2023 Not Ready for Inspection NICK DANERI
Deputy Steel/Welding 11/14/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 11/16/2023 Conditional Approval MICHAEL ROSENBERG
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Partial Approval LARRY ARNICK
Green Building Rough 11/17/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 11/17/2023 Not Ready for Inspection LARRY ARNICK
Green Building Rough 11/30/2023 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 11/30/2023 Not Ready for Inspection NICK DANERI
Wood Frame 11/30/2023 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval EDWIN GREGORYONA
Green Building Rough 12/11/2023 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 12/11/2023 Not Ready for Inspection EDWIN GREGORYONA
Green Building Rough 1/5/2024 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/5/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 1/5/2024 Not Ready for Inspection LARRY ARNICK
Deputy Drilled-In Anchors 1/29/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 2/14/2024 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 2/22/2024 Not Ready for Inspection JACOB MYERS
Insulation 2/22/2024 Approved JACOB MYERS
Verify Sprinkler Sign Off 2/22/2024 Not Ready for Inspection JACOB MYERS
Footing/Foundation/Slab 2/27/2024 Not Ready for Inspection NICK DANERI
Green Building Rough 2/27/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 2/27/2024 Partial Inspection NICK DANERI
Wood Frame 2/27/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/1/2024 Partial Approval NICK DANERI
Green Building Rough 4/17/2024 Not Ready for Inspection NICK DANERI
Verify Sprinkler Sign Off 4/17/2024 Not Ready for Inspection NICK DANERI
Wood Frame 4/17/2024 Partial Inspection NICK DANERI
Drywall Nailing 4/25/2024 Partial Approval NICK DANERI
Green Building Rough 4/25/2024 Not Ready for Inspection NICK DANERI
Insulation 4/25/2024 Partial Approval NICK DANERI
Drywall Nailing 5/8/2024 Partial Approval NICK DANERI
Green Building Rough 5/8/2024 Not Ready for Inspection NICK DANERI
Insulation 5/8/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 5/8/2024 Not Ready for Inspection NICK DANERI
Insulation 5/17/2024 Partial Approval NICK DANERI
Drywall Nailing 7/23/2024 Partial Approval NICK DANERI
Green Building Rough 7/23/2024 Not Ready for Inspection NICK DANERI
Insulation 7/23/2024 Approved NICK DANERI
Drywall Nailing 7/29/2024 Partial Approval NICK DANERI
Green Building Rough 7/29/2024 Approved NICK DANERI
Interior/Exterior Lathing 9/6/2024 Partial Approval JEROME BLACKWOOD
Masonry Wall/Backfill 9/6/2024 Partial Approval JEROME BLACKWOOD
Excavation/Setback/Form/Re-Bar 9/20/2024 Partial Approval LUIS CCAMACHO
Excavation/Setback/Form/Re-Bar 10/1/2024 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 10/23/2024 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 2/3/2025 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 2/26/2025 Partial Approval NICK DANERI
Drywall Nailing 3/12/2025 Approved NICK DANERI
Final 3/12/2025 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 3/12/2025 Not Ready for Inspection NICK DANERI
Green Building Final 3/12/2025 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready NICK DANERI
Smoke Detectors 3/12/2025 Partial Approval NICK DANERI
Verify Sprinkler Sign Off 3/12/2025 Not Ready for Inspection NICK DANERI
Wood Frame 3/12/2025 Not Ready for Inspection NICK DANERI
Final 5/8/2025 Not Ready for Inspection NICK DANERI
Footing/Foundation/Slab 5/8/2025 Approved NICK DANERI
Green Building Final 5/8/2025 Not Ready for Inspection NICK DANERI
SGSOV-Seismic Gas S/O Valve 5/8/2025 SGSOV Approved NICK DANERI
Smoke Detectors 5/8/2025 Approved NICK DANERI
Verify Sprinkler Sign Off 5/8/2025 Approved NICK DANERI
Wood Frame 5/8/2025 Approved NICK DANERI
Special/Order Compliance 5/27/2025 Partial Inspection NICK DANERI
Final 6/6/2025 Conditional Approval JOEY BUCHANAN
Green Building Final 6/6/2025 Approved JOEY BUCHANAN
Special/Order Compliance 6/10/2025 Approved JOEY BUCHANAN