1675-1677 W 37TH ST 90018
Certificate Information: 1675-1677 W 37TH ST 90018
- Application / Permit
- 19010-70000-05567
- Plan Check / Job No.
- B19SL01740
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2 STORY DUPLEX AND NEW 2CAR GARAGE. TYPE VB SPRINKLERED.
- Permit Issued
- Issued on 4/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2019 | RICARDO RAMIREZ |
| Green Plans Picked Up | 1/6/2020 | APPLICANT |
| Corrections Issued | 1/7/2020 | RICARDO RAMIREZ |
| Quality Review Completed | 1/9/2020 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 1/15/2020 | APPLICANT |
| Plan Check Approved | 3/3/2020 | RICARDO RAMIREZ |
| Issued | 4/16/2020 | LADBS |
| CofO in Progress | 6/16/2021 | ROBERT MCDOWELL |
| CofO in Progress | 6/16/2021 | ROBERT MCDOWELL |
| Permit Finaled | 6/30/2021 | DEROLD HAUFF |
| CofO Issued | 6/30/2021 | DEROLD HAUFF |
| Permit Finaled | 6/30/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 1/23/2020 | KHEDER ALRAZAA |
| Address approval | Cleared | 1/28/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 1/28/2020 | ROBERT DUFF |
| Sewer availability | Cleared | 1/28/2020 | THOMAS LANG |
| ZI | Cleared | 1/28/2020 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | EMIL KYUPELYAN |
| Low Impact Development | Cleared | 2/18/2020 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Soft Story Pros; Lic. No.: 1032036-B | P O BOX 35351 LOS ANGELES, CA 90035 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 7/9/2020 | Partial Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 7/9/2020 | Approved | JOSEPH MCGARRY |
| METHANE-Barrier | 7/9/2020 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 7/9/2020 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | ROBERT MCDOWELL |
| Underground Mechanical | 7/17/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2020 | Partial Approval | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/27/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 8/20/2020 | Partial Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| METHANE-Rough | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| PLUMBING-Rough | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 8/20/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Wood Frame | 8/20/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 9/8/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 9/8/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 9/8/2020 | Approved | ROBERT MCDOWELL |
| METHANE-Rough | 9/8/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Wood Frame | 9/8/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 9/28/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 9/28/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 1/25/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Sewer | 1/25/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Final | 4/30/2021 | Corrections Issued | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Green Building Final | 4/30/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 4/30/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 4/30/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Service/Power Release | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Smoke Detectors | 4/30/2021 | Approved | ROBERT MCDOWELL |
| Final | 5/12/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 5/19/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 5/27/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Final | 6/16/2021 | OK to Issue CofO | ROBERT MCDOWELL |