3549-3549 1/2 E 4TH ST 90063
Certificate Information: 3549-3549 1/2 E 4TH ST 90063
- Application / Permit
- 19010-70000-05503
- Plan Check / Job No.
- B19SL01721
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX AT REAR w/ 4 UNCOVERED PARKING STALLS
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | PRANITA SHAH |
| Green Plans Picked Up | 1/6/2020 | APPLICANT |
| Corrections Issued | 1/22/2020 | PRANITA SHAH |
| Quality Review Completed | 2/7/2020 | TU HUA |
| Building Plans Picked Up | 2/19/2020 | APPLICANT |
| Applicant returned to address corrections | 10/18/2023 | PRANITA SHAH |
| Plan Check Approved | 1/8/2024 | PRANITA SHAH |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | FREDDIE RIVERA |
| Permit Finaled | 5/22/2025 | DEROLD HAUFF |
| CofO Issued | 5/22/2025 | DEROLD HAUFF |
| Permit Finaled | 5/22/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 2/24/2020 | ANNA VIDAL |
| Permit | Cleared | 2/24/2020 | CELINA MORENO |
| ZI | Cleared | 2/24/2020 | ANNA VIDAL |
| Address approval | Cleared | 2/25/2020 | THOMAS LANG |
| Highway dedication | Cleared | 2/25/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 3/2/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/2/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 3/3/2020 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 3/3/2020 | JEREMY CARTER |
| Sewer availability | Cleared | 3/3/2020 | EMIL KYUPELYAN |
| Trees in Parkway | Cleared | 3/16/2020 | JOHN KIM |
| "Q" conditions | Cleared | 10/6/2023 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/6/2024 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 6/6/2024 | Partial Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 6/18/2024 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/18/2024 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2024 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2024 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 9/9/2024 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/6/2024 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/6/2024 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/7/2024 | Approved | FREDDIE RIVERA |
| Green Building Rough | 11/7/2024 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 11/7/2024 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 11/7/2024 | Approved | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | FREDDIE RIVERA |
| Insulation | 11/12/2024 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/21/2024 | Approved | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/21/2024 | Approved | ANTHONY RAMOS |
| Gas Test | 1/16/2025 | Partial Approval | FREDDIE RIVERA |
| Sewer | 1/16/2025 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 1/16/2025 | Partial Approval | FREDDIE RIVERA |
| Verify Rec and Parks Fee Memo | 1/16/2025 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 1/22/2025 | Partial Approval | JUSTIN HAWLEY |
| ELECTRICAL-Final | 4/30/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 4/30/2025 | Approved | ARTHUR NEGRETE |
| MERV13>=Final | 4/30/2025 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Approved | ARTHUR NEGRETE |
| Smoke Detectors | 4/30/2025 | Approved | ARTHUR NEGRETE |
| Final | 5/15/2025 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 5/15/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 5/15/2025 | Approved | FREDDIE RIVERA |
| Service/Power Release | 5/15/2025 | Approved | FREDDIE RIVERA |