5462 W GEER AVE 90016
Certificate Information: 5462 W GEER AVE 90016
- Application / Permit
- 19010-70000-05364
- Plan Check / Job No.
- B19SL01684
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3 STORY SINGLE FAMILY DWELLING RESIDENCE WITH ATTACHED GARAGE
- Permit Issued
- Issued on 10/26/2020
- Issuing Office
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | TEODORO DIAZ RODRIGUEZ |
| Corrections Issued | 12/20/2019 | TEODORO DIAZ RODRIGUEZ |
| Quality Review Completed | 1/16/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 6/4/2020 | APPLICANT |
| Plan Check Approved | 9/3/2020 | TEODORO DIAZ RODRIGUEZ |
| Issued | 10/26/2020 | APPLICANT |
| Building Plans Picked Up | 10/27/2020 | APPLICANT |
| CofO in Progress | 11/19/2021 | JOSE AVILA |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
| CofO Issued | 12/3/2021 | DEROLD HAUFF |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 1/21/2020 | DONALD CRICHLOW |
| Green Code | Cleared | 1/21/2020 | DONALD CRICHLOW |
| Address approval | Cleared | 1/29/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | JEANIE LAM |
| Sewer availability | Cleared | 1/29/2020 | JEANIE LAM |
| Low Impact Development | Cleared | 5/26/2020 | ORVAL HERNANDEZ-MARCIAL |
| Frnt yard landscape/Water mgmt | Cleared | 6/9/2020 | DANIEL CORONADO |
| Roof/Waste drainage to street | Cleared | 7/20/2020 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 8/28/2020 | KURT CORRAL |
Contact Information
| Contractor | Blue Phoenix Builders Inc; Lic. No.: 1066549-B | 4474 W ADAMS BLVD #205 LOS ANGELES, CA 90016 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 12/21/2020 | Partial Inspection | DAVID CHAN |
| PLUMBING-Rough | 12/24/2020 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 12/30/2020 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 12/31/2020 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 12/31/2020 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 1/15/2021 | Approved | DAVID CHAN |
| Underground Mechanical | 1/28/2021 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2021 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/13/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 4/13/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 4/13/2021 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 4/21/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/3/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/3/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/3/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 5/3/2021 | Approved | STUART CHAPMAN |
| Insulation | 5/11/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 5/11/2021 | Partial Approval | STUART CHAPMAN |
| Insulation | 5/12/2021 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 5/12/2021 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 5/26/2021 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 6/7/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/15/2021 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 7/2/2021 | Approved | RUBEN SALAS |
| ELECTRICAL-Final | 9/8/2021 | Corrections Issued | DAVID FEILER |
| Gas Test | 9/8/2021 | Approved | DAVID FEILER |
| HVAC-Final | 9/8/2021 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 10/28/2021 | Not Ready for Inspection | JOSE AVILA |
| Gas Test | 10/28/2021 | Approved | JOSE AVILA |
| HVAC-Final | 10/28/2021 | Partial Approval | JOSE AVILA |
| PLUMBING-Final | 10/28/2021 | Not Ready for Inspection | JOSE AVILA |
| ELECTRICAL-Final | 11/3/2021 | Approved | JOSE AVILA |
| HVAC-Final | 11/3/2021 | Approved | JOSE AVILA |
| PLUMBING-Final | 11/3/2021 | Approved | JOSE AVILA |
| Final | 11/12/2021 | Corrections Issued | JOSE AVILA |
| Green Building Final | 11/12/2021 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Approved | JOSE AVILA |
| Service/Power Release | 11/12/2021 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 11/12/2021 | Approved | JOSE AVILA |
| Final | 11/18/2021 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 11/18/2021 | Approved | JOSE AVILA |