2853 E CINCINNATI ST 90033

Certificate Information: 2853 E CINCINNATI ST 90033

Application / Permit
19010-70000-05351
Plan Check / Job No.
B19SL01678
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. TYPE VB FULLY SPRINKLERED.
Permit Issued
Issued on 3/13/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 4/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 RICARDO RAMIREZ
Green Plans Picked Up 12/18/2019 APPLICANT
Corrections Issued 12/19/2019 RICARDO RAMIREZ
Quality Review Completed 12/24/2019 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/26/2019 APPLICANT
Plan Check Approved 1/23/2020 RICARDO RAMIREZ
Issued 3/13/2020 LADBS
CofO in Progress 2/26/2021 OSVALDO PARAMO
Permit Finaled 4/16/2021 DEROLD HAUFF
Permit Finaled 4/16/2021 DEROLD HAUFF
CofO Issued 4/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/10/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 1/10/2020 GEORGE SUCHAND
Sewer availability Cleared 1/10/2020 EMIL KYUPELYAN
Green Code Cleared 1/17/2020 DONALD CRICHLOW
Low Impact Development Cleared 1/17/2020 ORVAL HERNANDEZ-MARCIAL
Frnt yard landscape/Water mgmt Cleared 1/21/2020 JOE LUCKEY
Roof/Waste drainage to street Cleared 1/21/2020 ERIK BEASLEY
GPI Written Notices Cleared 1/23/2020 RICARDO RAMIREZ
Grading Pre-Inspection Cleared 1/23/2020 RICARDO RAMIREZ

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 7366 W MANCHESTER AVE #B      LOS ANGELES, CA 90045
Geologist Feucht,, Alex Thomas; Lic. No.: GEO4433 2443 EAGLE HARBOR DRIVE      HENDERSON, NV 890527136

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/6/2020 Partial Approval OSVALDO PARAMO
Underground Mechanical 5/6/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/11/2020 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 5/11/2020 Conditional Approval CRAIG VAUGHAN
METHANE-Barrier 5/11/2020 Approved CRAIG VAUGHAN
METHANE-Subgrade 5/11/2020 Approved CRAIG VAUGHAN
Deputy Wood Construction 5/28/2020 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/28/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Approved OSVALDO PARAMO
HVAC-Rough 7/27/2020 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 7/27/2020 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 7/30/2020 Corrections Issued OSVALDO PARAMO
BUILDING-Rough-Frame 7/31/2020 Partial Inspection RUBEN SALAS
Green Building Rough 7/31/2020 Partial Inspection RUBEN SALAS
METHANE-Rough 7/31/2020 Partial Inspection RUBEN SALAS
Verify Sprinkler Sign Off 7/31/2020 Partial Inspection RUBEN SALAS
Rough-Elec/Plmb/HVAC 8/4/2020 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/7/2020 Approved OSVALDO PARAMO
Green Building Rough 8/7/2020 Approved OSVALDO PARAMO
METHANE-Rough 8/7/2020 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 8/7/2020 Approved OSVALDO PARAMO
Insulation 8/13/2020 Corrections Issued CHRISTOPHER DELLEFIELD
Insulation 8/18/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 8/21/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/21/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 8/27/2020 Approved THOMAS LOGRASSO
Gas Test 9/30/2020 Approved OSVALDO PARAMO
Sewer 9/30/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 2/8/2021 Not Ready for Inspection OSVALDO PARAMO
Final 2/8/2021 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 2/8/2021 Approved OSVALDO PARAMO
PLUMBING-Final 2/8/2021 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Final 2/9/2021 Approved OSVALDO PARAMO
Gas Test 2/9/2021 Approved OSVALDO PARAMO
PLUMBING-Final 2/9/2021 Approved OSVALDO PARAMO
HVAC-Final 2/18/2021 Approved OSVALDO PARAMO
Final 2/25/2021 OK to Issue CofO OSVALDO PARAMO
Green Building Final 2/25/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 2/25/2021 SGSOV Approved OSVALDO PARAMO
Service/Power Release 2/25/2021 Approved OSVALDO PARAMO
Smoke Detectors 2/25/2021 Approved OSVALDO PARAMO