5335 W HOMESIDE AVE 90016

Certificate Information: 5335 W HOMESIDE AVE 90016

Application / Permit
19010-70000-05245
Plan Check / Job No.
B19SL01649
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SFD (FRONT BUILDING)
Permit Issued
Issued on 10/28/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Green Plans Picked Up 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 EMMANUEL MARTINEZ
Corrections Issued 12/9/2019 EMMANUEL MARTINEZ
Quality Review Completed 12/24/2019 ARMEN JIVALAGIAN
Building Plans Picked Up 1/3/2020 APPLICANT
Plan Check Approved 3/11/2020 STARR CHEN
Issued 10/28/2020 APPLICANT
CofO in Progress 1/3/2022 JOSE AVILA
Permit Finaled 1/22/2022 DEROLD HAUFF
CofO Issued 1/22/2022 DEROLD HAUFF
Permit Finaled 1/22/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/19/2019 THOMAS LANG
Highway dedication Cleared 1/21/2020 JEANIE LAM
Permit Cleared 1/21/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/29/2020 ERIK BEASLEY
Hydrant and Access approval Cleared 1/29/2020 GEORGE SUCHAND
Sewer availability Cleared 1/29/2020 ERIK BEASLEY
Trees in Parkway Cleared 1/31/2020 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 2/18/2020 JOE LUCKEY
Green Code Cleared 2/19/2020 VIVIAN LAO
Low Impact Development Cleared 3/2/2020 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 3/2/2020 WALLIE JONG

Contact Information

Contractor Baksh Construction Inc; Lic. No.: 910533-B 4 HILLCREST MANOR      ROLLING HILLS ESTATES, CA 90274
Engineer Mendoza,, Fabian; Lic. No.: C90183 PO BOX 2305      NORWALK, CA 90651
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2021 Not Ready for Inspection DAVID CHAN
BUILDING-Rough-Frame 2/8/2021 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 2/8/2021 Corrections Issued KATHRYN BUTTERWORTH
Insulation 2/10/2021 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Rough 2/10/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/12/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Not Ready for Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 5/17/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 5/17/2021 Approved STUART CHAPMAN
Green Building Rough 5/17/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 5/17/2021 Conditional Approval STUART CHAPMAN
PLUMBING-Rough 5/17/2021 Approved STUART CHAPMAN
Rough-Elec/Plmb/HVAC 5/17/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 5/17/2021 Approved STUART CHAPMAN
Insulation 5/27/2021 Approved RUBEN SALAS
Drywall Nailing 6/4/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/4/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/8/2021 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 11/30/2021 Partial Approval JOSE AVILA
ELECTRICAL-Final 11/30/2021 Corrections Issued JOSE AVILA
Final 11/30/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 11/30/2021 Corrections Issued JOSE AVILA
Green Building Final 11/30/2021 Approved JOSE AVILA
Green Building Rough 11/30/2021 Approved JOSE AVILA
HVAC-Final 11/30/2021 Partial Approval JOSE AVILA
PLUMBING-Final 11/30/2021 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/30/2021 SGSOV Approved JOSE AVILA
Service/Power Release 11/30/2021 Corrections Issued JOSE AVILA
Smoke Detectors 11/30/2021 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 12/3/2021 Approved JOSE AVILA
ELECTRICAL-Final 12/3/2021 Approved JOSE AVILA
Final 12/3/2021 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/3/2021 Approved JOSE AVILA
Service/Power Release 12/3/2021 Approved JOSE AVILA
Smoke Detectors 12/3/2021 Approved JOSE AVILA
Service/Power Release 12/15/2021 Approved JOSE AVILA
ELECTRICAL-Final 12/30/2021 Approved JOSE AVILA
Final 12/30/2021 OK to Issue CofO JOSE AVILA
HVAC-Final 12/30/2021 Approved JOSE AVILA
PLUMBING-Final 12/30/2021 Approved JOSE AVILA
Service/Power Release 12/30/2021 Approved JOSE AVILA