4020 W 63RD ST 90043
Certificate Information: 4020 W 63RD ST 90043
- Application / Permit
- 19010-70000-05222
- Plan Check / Job No.
- B19SL01637
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 PER WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | MIGUEL JIMENEZ |
| Corrections Issued | 12/18/2019 | MIGUEL JIMENEZ |
| Quality Review Completed | 12/24/2019 | BILL STUTSMAN |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Green Plans Picked Up | 2/12/2020 | APPLICANT |
| Applicant returned to address corrections | 7/9/2020 | JOHNNY WU |
| Plan Check Approved | 7/9/2020 | JOHNNY WU |
| Issued | 5/6/2021 | APPLICANT |
| CofO in Progress | 12/9/2021 | FREDDIE RIVERA |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
| CofO Issued | 2/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 1/6/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/6/2020 | EMIL KYUPELYAN |
| Construction near power lines | Cleared | 3/5/2020 | OSCAR CASTRO |
| Grading Pre-Inspection | Cleared | 3/12/2020 | PATRICK MISCHLICH |
| Green Code | Cleared | 3/12/2020 | COLIN LOREDO |
| GPI Written Notices | Cleared | 7/9/2020 | MIGUEL JIMENEZ |
Contact Information
| Contractor | Roston Thomas Construction; Lic. No.: 954624-B | P O BOX 351292 LOS ANGELES, CA 90035 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/21/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/21/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/7/2021 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 7/7/2021 | Approved | ANSON MAGLASANG |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2021 | Partial Approval | ANSON MAGLASANG |
| Green Building Rough | 7/7/2021 | No Access for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 7/7/2021 | Corrections Issued | ANSON MAGLASANG |
| Sewer | 7/7/2021 | Partial Approval | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 7/15/2021 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 7/15/2021 | Corrections Issued | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 7/15/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 7/20/2021 | Partial Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/26/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 7/26/2021 | Approved | DAVID FEILER |
| Green Building Rough | 7/26/2021 | Approved | DAVID FEILER |
| Insulation | 7/26/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 8/19/2021 | Approved | FREDDIE RIVERA |
| Final | 10/26/2021 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 10/26/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 10/26/2021 | Approved | FREDDIE RIVERA |
| Final | 11/1/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 11/1/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 11/1/2021 | Approved | FREDDIE RIVERA |
| Special/Order Compliance | 11/4/2021 | Corrections Issued | FREDDIE RIVERA |
| Final | 11/10/2021 | Conditional Approval | FREDDIE RIVERA |