19633 W STRATHERN ST 91335
Certificate Information: 19633 W STRATHERN ST 91335
- Application / Permit
- 19010-70000-05046
- Plan Check / Job No.
- B19SL01582
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. AT REAR
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2019 | MONICA RAMIREZ |
| Corrections Issued | 1/2/2020 | EVERARDO SANTOS |
| Quality Review Completed | 1/7/2020 | LAWRENCE QUIRANTE |
| Green Plans Picked Up | 4/24/2020 | APPLICANT |
| Applicant returned to address corrections | 1/6/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/7/2021 | MONICA RAMIREZ |
| Building Plans Picked Up | 1/8/2021 | APPLICANT |
| Applicant returned to address corrections | 1/19/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/1/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/8/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 3/15/2021 | MONICA RAMIREZ |
| Plan Check Approved | 3/18/2021 | MONICA RAMIREZ |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 5/9/2022 | VINCENT HANLEY |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Green Code | Cleared | 4/21/2020 | KHEDER ALRAZAA |
| Address approval | Cleared | 5/20/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 5/20/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 9/16/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/16/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 11/30/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Liel Construction Inc; Lic. No.: 929105-B | 11690 OVERLAND DRIVE FONTANA, CA 92337 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/16/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/3/2021 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/3/2021 | Approved | VINCENT HANLEY |
| Insulation | 5/3/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/3/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2021 | OK to Expire Permit | VINCENT HANLEY |
| Grounding or Bonding | 5/12/2021 | Approved | VINCENT HANLEY |
| Insulation | 5/12/2021 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/21/2021 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2021 | Approved | VINCENT HANLEY |
| Grounding or Bonding | 7/21/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 7/21/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 7/21/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 7/21/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/13/2021 | Approved | VINCENT HANLEY |
| Insulation | 8/13/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/13/2021 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 8/13/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 8/13/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 8/25/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 8/25/2021 | Approved | DAVID SANDOVAL |
| Sewer | 8/25/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Final | 10/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Sewer | 10/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Underground Mechanical | 10/20/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Sewer | 11/2/2021 | Approved | VINCENT HANLEY |
| Underground Mechanical | 11/2/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/13/2022 | Approved | VINCENT HANLEY |
| Final | 4/13/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Final | 4/13/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 4/13/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 4/13/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/13/2022 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 4/13/2022 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/13/2022 | Approved | VINCENT HANLEY |