23060 W LEONORA DR 91367
Certificate Information: 23060 W LEONORA DR 91367
- Application / Permit
- 19010-70000-05044
- Plan Check / Job No.
- B19SL01580
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WOOD FRAME PRESPECTIVE PROVISIONS.
- Permit Issued
- Issued on 4/28/2020
- Issuing Office
- Current Status
- CofO Issued on 1/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | MIGUEL JIMENEZ |
| Corrections Issued | 12/5/2019 | MIGUEL JIMENEZ |
| Quality Review Completed | 12/13/2019 | BILL STUTSMAN |
| Green Plans Picked Up | 12/31/2019 | APPLICANT |
| Building Plans Picked Up | 1/23/2020 | APPLICANT |
| Applicant returned to address corrections | 4/13/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 4/16/2020 | ARSALAN SHABESTARI |
| Issued | 4/28/2020 | APPLICANT |
| CofO in Progress | 1/20/2021 | TROY SANDERS |
| Permit Finaled | 1/20/2021 | JOHN JANSON |
| CofO Issued | 1/20/2021 | JOHN JANSON |
| Permit Finaled | 1/20/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2020 | JEANETTE VONG |
| Construction near power lines | Cleared | 1/28/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2020 | JAMES MORALEZ |
| Hydrant and Access approval | Cleared | 2/14/2020 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 2/14/2020 | JAMES MORALEZ |
| Sewer availability | Cleared | 2/14/2020 | JAMES MORALEZ |
| Green Code | Cleared | 4/6/2020 | COLIN LOREDO |
Contact Information
| Contractor | Olympia Construction Inc; Lic. No.: 1005351-B | 5510 SEPULVEDA BLVD #122 SHERMAN OAKS, CA 91411 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/29/2020 | Corrections Issued | HENRY KIM |
| Footing/Foundation/Slab | 6/11/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 7/7/2020 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2020 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 9/9/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 9/9/2020 | Approved | TROY SANDERS |
| Green Building Rough | 9/9/2020 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 9/9/2020 | Approved | TROY SANDERS |
| MERV13>=Rough | 9/9/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 9/9/2020 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 9/9/2020 | Approved | TROY SANDERS |
| Green Building Rough | 9/21/2020 | Approved | TROY SANDERS |
| Insulation | 9/21/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/21/2020 | Approved | TROY SANDERS |
| Shower Pan | 9/21/2020 | Approved | TROY SANDERS |
| Drywall Nailing | 9/24/2020 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 9/24/2020 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 12/31/2020 | Approved | TROY SANDERS |
| Final | 12/31/2020 | Corrections Issued | TROY SANDERS |
| Green Building Final | 12/31/2020 | Approved | TROY SANDERS |
| HVAC-Final | 12/31/2020 | Approved | TROY SANDERS |
| MERV13>=Final | 12/31/2020 | Approved | TROY SANDERS |
| PLUMBING-Final | 12/31/2020 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/31/2020 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 12/31/2020 | Not Ready for Inspection | TROY SANDERS |
| Smoke Detectors | 12/31/2020 | Approved | TROY SANDERS |
| Final | 1/8/2021 | Not Ready for Inspection | TROY SANDERS |
| Service/Power Release | 1/8/2021 | Approved | TROY SANDERS |
| Final | 1/19/2021 | OK to Issue CofO | TROY SANDERS |