5466 S 8TH AVE 90043
Certificate Information: 5466 S 8TH AVE 90043
- Application / Permit
- 19010-70000-04970
- Plan Check / Job No.
- B19SL01555
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ACCESSORY DWELLING UNIT WITH ATTACHED 2-CAR GARAGE AT REAR OF LOT
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | PRANITA SHAH |
| Corrections Issued | 11/26/2019 | PRANITA SHAH |
| Quality Review Completed | 12/4/2019 | TU HUA |
| Green Plans Picked Up | 12/5/2019 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | PRANITA SHAH |
| Plan Check Approved | 1/28/2022 | PRANITA SHAH |
| No Progress | 1/28/2022 | PRANITA SHAH |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| Plan Check Approved | 5/4/2022 | PRANITA SHAH |
| Issued | 5/23/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | ANTHONY EGSON |
| Permit Finaled | 1/31/2023 | DEROLD HAUFF |
| CofO Issued | 1/31/2023 | DEROLD HAUFF |
| Permit Finaled | 1/31/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/18/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2020 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 2/18/2020 | ROBERT DUFF |
| Sewer availability | Cleared | 2/18/2020 | ELAINE LEI |
| Construction near power lines | Cleared | 5/7/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 11/2/2021 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 11/5/2021 | ABEL CASILLAS |
| Green Code | Cleared | 1/28/2022 | COLIN LOREDO |
Contact Information
| Contractor | Gemilyan Karen; Lic. No.: 801955-B | 4606 WILLIS AVE #307 SHERMAN OAKS, CA 91403 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 5/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/27/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 6/13/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 6/16/2022 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/24/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 6/24/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/15/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/15/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 8/15/2022 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 8/15/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/18/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/18/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 8/18/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 8/26/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 8/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 8/26/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 8/26/2022 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 9/1/2022 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 9/1/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 9/1/2022 | Approved | ANTHONY EGSON |
| Insulation | 9/8/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/8/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 9/19/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 9/19/2022 | Approved | ANTHONY EGSON |
| Sewer | 11/4/2022 | Approved | ANTHONY EGSON |
| Gas Test | 12/13/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/19/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/19/2022 | No Access for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 12/19/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | ANTHONY EGSON |
| Final | 12/23/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 12/23/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/23/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/23/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 12/23/2022 | Approved | ANTHONY EGSON |
| Smoke Detectors | 12/23/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/30/2022 | Approved | ANTHONY EGSON |
| Final | 12/30/2022 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 12/30/2022 | Approved | ANTHONY EGSON |