2118 S PORTLAND ST 90007
Certificate Information: 2118 S PORTLAND ST 90007
- Application / Permit
- 19010-70000-04951
- Plan Check / Job No.
- B19SL01549
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/26/2021
- Issuing Office
- Current Status
- CofO Issued on 1/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | FERNANDO FLORES |
| Corrections Issued | 12/5/2019 | FERNANDO FLORES |
| Quality Review Completed | 12/23/2019 | ARMEN JIVALAGIAN |
| Green Plans Picked Up | 7/2/2020 | APPLICANT |
| Plan Check Approved | 8/5/2020 | FERNANDO FLORES |
| Issued | 2/26/2021 | APPLICANT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| CofO in Progress | 10/20/2022 | HORACE FULTZ |
| CofO Issued | 1/4/2023 | DEROLD HAUFF |
| Permit Finaled | 1/4/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2019 | THOMAS LANG |
| Low Impact Development | Cleared | 12/20/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 12/20/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/20/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 12/23/2019 | JEREMY CARTER |
| HPOZ | Cleared | 12/30/2019 | KATIE DEBIASE |
| ZI | Cleared | 12/30/2019 | KATIE DEBIASE |
| Green Code | Cleared | 5/7/2020 | FERNANDO FLORES |
| "Q" conditions | Cleared | 5/8/2020 | MAXFIELD VERMY |
| ZI | Cleared | 6/2/2020 | MAXFIELD VERMY |
| Miscellaneous | Cleared | 7/28/2020 | MAXFIELD VERMY |
Contact Information
| Contractor | Gomez Construction; Lic. No.: 1049981-B | 1151 S ALMA AVE LOS ANGELES, CA 90023 |
| Engineer | Arriola,, Kirby Norman; Lic. No.: C31416 | PO BOX 5566 OXNARD, CA 93031 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/8/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 7/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 7/12/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 7/12/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 8/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Underground Mechanical | 8/18/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 8/20/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 8/20/2021 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 8/20/2021 | Approved | JOAQUIN GREENOUGH |
| Insulation | 8/23/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2021 | Partial Approval | HORACE FULTZ |
| Wood Frame | 10/4/2021 | Partial Approval | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 2/28/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 2/28/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 3/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 3/4/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 3/4/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 3/4/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 3/4/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 3/4/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 4/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 4/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Rough | 4/26/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/26/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 4/26/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/9/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/9/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 5/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/13/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/13/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 5/23/2022 | Approved | JOAQUIN GREENOUGH |
| Structural Steel Frame | 5/23/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 6/3/2022 | Off-Hour Fees Due | |
| BUILDING-Rough-Frame | 6/8/2022 | Partial Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 6/21/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/5/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 7/5/2022 | Partial Approval | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/8/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 7/8/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 9/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 9/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Final | 9/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 9/20/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 9/30/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Final | 9/30/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Final | 9/30/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| HVAC-Final | 9/30/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| PLUMBING-Final | 9/30/2022 | Partial Approval | SHAVONNE ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | SHAVONNE ESPINOZA |
| Service/Power Release | 9/30/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Smoke Detectors | 9/30/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Wood Frame | 9/30/2022 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 10/4/2022 | Partial Approval | SHAVONNE ESPINOZA |
| PLUMBING-Final | 10/4/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Service/Power Release | 10/4/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 10/6/2022 | Corrections Issued | HORACE FULTZ |
| Final | 10/6/2022 | Corrections Issued | HORACE FULTZ |
| Green Building Final | 10/6/2022 | Approved | HORACE FULTZ |
| HVAC-Final | 10/6/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 10/6/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | HORACE FULTZ |
| Smoke Detectors | 10/6/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 10/20/2022 | Approved | HORACE FULTZ |
| Final | 10/20/2022 | OK to Issue CofO | HORACE FULTZ |
| Service/Power Release | 10/20/2022 | Approved | HORACE FULTZ |