241-241 1/2 W 98TH ST 90003

Certificate Information: 241-241 1/2 W 98TH ST 90003

Application / Permit
19010-70000-04871
Plan Check / Job No.
B19SL01531
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 2 STORY DUPLEX AT REAR OF LOT
Permit Issued
Issued on 9/8/2021
Issuing Office
Current Status
CofO Issued on 5/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 VU NGUYEN
Corrections Issued 11/19/2019 VU NGUYEN
Quality Review Completed 11/27/2019 JOSE RODRIGUEZ
Green Plans Picked Up 1/16/2020 APPLICANT
Applicant returned to address corrections 5/21/2020 VU NGUYEN
Applicant returned to address corrections 7/21/2020 VU NGUYEN
Applicant returned to address corrections 11/10/2020 VU NGUYEN
Applicant returned to address corrections 11/19/2020 VU NGUYEN
Plan Check Approved 5/13/2021 VU NGUYEN
Issued 9/8/2021 APPLICANT
Building Plans Picked Up 9/24/2021 APPLICANT
CofO in Progress 5/8/2026 ARTHUR NEGRETE
Permit Finaled 5/18/2026 ANSON MAGLASANG
CofO Issued 5/18/2026 ANSON MAGLASANG
Permit Finaled 5/18/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 3/9/2020 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 3/9/2020 COLLINS ALLAN
Eng Process Fee Ord 176,300 Cleared 3/9/2020 EMIL KYUPELYAN
Hydrant and Access approval Cleared 3/9/2020 JEREMY CARTER
Sewer availability Cleared 3/9/2020 EMIL KYUPELYAN
Green Code Cleared 3/18/2020 VU NGUYEN
Low Impact Development Cleared 9/29/2020 ROBIN YAMADA
Community Plan Implem. Overlay Cleared 11/18/2020 SAM NAVID
Roof/Waste drainage to street Cleared 11/18/2020 WALLIE JONG
Permit Cleared 12/1/2020 WALLIE JONG
Community Plan Implem. Overlay Cleared 12/14/2020 HELEN JADALI
Community Plan Implem. Overlay Cleared 12/29/2020 JOHN KIM
ZI Cleared 4/29/2021 DAVID URITA
Community Plan Implem. Overlay Cleared 5/13/2021 RIDWAN HARDY

Contact Information

Contractor Frost Construction; Lic. No.: 580847-B 1041 WEST 105TH STREET      LOS ANGELES, CA 90044
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/18/2021 Corrections Issued CRAIG DAVIS
Underground Mechanical 10/18/2021 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 10/19/2021 Approved CRAIG DAVIS
Footing/Foundation/Slab 10/22/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 10/27/2021 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/29/2021 Approved EUGENE CASSIDY
Underground Mechanical 10/29/2021 Approved EUGENE CASSIDY
Drywall Nailing 12/7/2021 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 2/4/2022 Approved JOHN KLARIN
Insulation 2/10/2022 Approved JOHN KLARIN
Interior/Exterior Lathing 2/10/2022 Approved JOHN KLARIN
Drywall Nailing 2/23/2022 Approved JOHN KLARIN
Gas Test 7/1/2022 Partial Approval ALIZAH MAYAGOITIA
Sewer 7/1/2022 Approved ALIZAH MAYAGOITIA
Pre-Inspection 8/26/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/4/2023 Partial Approval JOHN KLARIN
Final 10/4/2023 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 10/4/2023 Approved JOHN KLARIN
Green Building Final 10/4/2023 Corrections Issued JOHN KLARIN
Green Building Rough 10/4/2023 Approved JOHN KLARIN
MERV13>=Final 10/4/2023 Corrections Issued JOHN KLARIN
MERV13>=Rough 10/4/2023 Corrections Issued JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 10/4/2023 SGSOV Not Ready JOHN KLARIN
Service/Power Release 10/4/2023 Not Ready for Inspection JOHN KLARIN
Smoke Detectors 10/4/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 10/4/2023 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 12/8/2023 Corrections Issued JOHN KLARIN
Final 12/8/2023 Corrections Issued JOHN KLARIN
Green Building Final 12/8/2023 Corrections Issued JOHN KLARIN
MERV13>=Final 12/8/2023 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 12/8/2023 Not Ready for Inspection JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Approved JOHN KLARIN
Service/Power Release 12/8/2023 Not Ready for Inspection JOHN KLARIN
Verify Sprinkler Sign Off 12/8/2023 Corrections Issued JOHN KLARIN
Pre-Inspection 1/10/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Final 1/16/2025 Approved ANTHONY EGSON
HVAC-Final 1/16/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Final 1/16/2025 Corrections Issued ANTHONY EGSON
Smoke Detectors 1/16/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 3/20/2025 Approved ANTHONY EGSON
Final 3/20/2025 Not Ready for Inspection ANTHONY EGSON
Gas Test 3/20/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Final 3/20/2025 Approved ANTHONY EGSON
HVAC-Final 3/20/2025 Approved ANTHONY EGSON
MERV13>=Final 3/20/2025 Approved ANTHONY EGSON
MERV13>=Rough 3/20/2025 Approved ANTHONY EGSON
PLUMBING-Final 3/20/2025 Not Ready for Inspection ANTHONY EGSON
Service/Power Release 3/20/2025 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 3/20/2025 Approved ANTHONY EGSON
Final 7/7/2025 Not Ready for Inspection ANTHONY EGSON
Gas Test 7/7/2025 Approved ANTHONY EGSON
PLUMBING-Final 7/7/2025 Approved ANTHONY EGSON
Service/Power Release 7/7/2025 Corrections Issued ANTHONY EGSON
Verify Rec and Parks Fee Memo 7/7/2025 Approved ANTHONY EGSON
Final 4/16/2026 Corrections Issued ARTHUR NEGRETE
Service/Power Release 4/16/2026 Approved ARTHUR NEGRETE
Final 5/7/2026 OK to Issue CofO ARTHUR NEGRETE