608-608 1/2 W 42ND ST 90037
Certificate Information: 608-608 1/2 W 42ND ST 90037
- Application / Permit
- 19010-70000-04782
- Plan Check / Job No.
- B19SL01495
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3 STORY DUPLEX W/ ATTACHED GARAGE.
- Permit Issued
- Issued on 1/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | JOE VO |
| Corrections Issued | 11/5/2019 | JOE VO |
| Quality Review Completed | 11/14/2019 | KEN GILL |
| Green Plans Picked Up | 4/1/2020 | APPLICANT |
| Plan Check Approved | 8/31/2020 | JOE VO |
| Issued | 1/12/2021 | APPLICANT |
| Building Plans Picked Up | 1/14/2021 | APPLICANT |
| CofO in Progress | 2/7/2022 | SABAS ALONSO |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
| CofO Issued | 2/14/2022 | DEROLD HAUFF |
| Permit Finaled | 2/14/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2019 | EMIL KYUPELYAN |
| Permit | Cleared | 12/9/2019 | EMIL KYUPELYAN |
| ZA Case | Cleared | 12/17/2019 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/13/2020 | ERIK BEASLEY |
| Green Code | Cleared | 4/1/2020 | VIVIAN LAO |
| Hydrant and Access approval | Cleared | 4/14/2020 | JEREMY CARTER |
| Low Impact Development | Cleared | 8/6/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/13/2020 | JEANIE LAM |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/16/2021 | Approved | ROBERT MCDOWELL |
| Underground Mechanical | 3/16/2021 | Approved | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 3/23/2021 | Partial Approval | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/26/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 5/26/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/26/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| HVAC-Rough | 5/26/2021 | Approved | ROBERT MCDOWELL |
| MERV13>=Rough | 5/26/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 5/26/2021 | Approved | ROBERT MCDOWELL |
| Verify Sprinkler Sign Off | 5/26/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Insulation | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 6/3/2021 | Approved | ROBERT MCDOWELL |
| Special/Order Compliance | 8/6/2021 | Partial Inspection | CALEB MEISTER |
| Special/Order Compliance | 8/9/2021 | Approved | CALEB MEISTER |
| Special/Order Compliance | 8/9/2021 | Partial Inspection | WILLIAM WREN |
| Final | 12/10/2021 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 12/10/2021 | Approved | SABAS ALONSO |
| Green Building Final | 12/10/2021 | Approved | SABAS ALONSO |
| MERV13>=Final | 12/10/2021 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/10/2021 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 12/10/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 12/10/2021 | Approved | SABAS ALONSO |
| Final | 2/7/2022 | OK to Issue CofO | SABAS ALONSO |